The PDF version pdf file
Display Related Directives to this directive.
Display Reference Documents to this directive.

U.S. Department of Energy				DOE G 413.3-10
Washington, D.C. 20585
							5-6-08

		    EARNED VALUE MANAGEMENT SYSTEM (EVMS)
						  
[This Guide describes suggested nonmandatory approaches for
meeting requirements. Guides are not requirements documents and
are not to be construed as requirements in any audit or appraisal
for compliance with the parent Policy, Order, Notice, or Manual.]
						  
						  
					   FOREWORD
						  
This Department of Energy (DOE) Guide is for use by all DOE
elements. This Guide intends to provide approaches for
implementing the Earned Value Management System (EVMS)
requirements of DOE O 413.3A, Program and Project Management for
the Acquisition of Capital Assets in compliance with the American
National Standards Institute/Electronic Industries Alliance
(ANSI/EIA)-748, Earned Value Management Systems. DOE Guides,
which are part of the DOE Directives System, provide supplemental
information for fulfilling requirements contained in rules,
regulatory standards, and DOE directives. Guides do not establish
or invoke new requirements or are they substitutes for
requirements.

				 SECTION I-INTRODUCTION
						  
1.	GOAL
	
	To support DOE's initiatives to improve program, project,
	and contract management through the implementation and
	surveillance of a contractor's EVMS that is in conformance
	with DOE O 413.3A and the American National Standards
	Institute/Electronic Industries Alliance (ANSI/EIA)-748,
	Earned Value Management System.
	
	The primary audience of this Guide is the FPD. It is
	critical that the federal project director (FPD) understands
	the EVMS process and procedures and utilizes the EVMS
	information as an effective project management system to
	ensure successful project execution and to fulfill their
	roles and responsibilities as outlined in DOE O 413.3A.
	
2.	OBJECTIVE
	
	To provide an overview of the DOE EVMS that:
  
	a.	Describes the EVMS and associated critical information
		available to the FPD, federal program manager, other
		senior leaders, and contractors, and suggests how to
		use them. To these ends, this guide:
		
		(1)	Suggests a common reporting format to communicate
			EVMS consistently across DOE.
			
		(2)	Promotes implementation of EVMS as early in a
			project life cycle as practical.
			
	b.	Describes the certification process for a contractor's
		EVMS. See SECTION III.
		
	c.	Describes the EVMS surveillance process to ensure
		ongoing EVMS compliance. See SECTION IV.
		
	d.	Describes EVMS-related lessons learned. See SECTION V.
		
	This guide is not intended to be a comprehensive training
	document, a detailed system requirement, or a contractual
	implementation requirement. Those issues are beyond the
	scope of this guide; however, FPDs and other DOE elements
	are encouraged to contact the Office of Engineering and
	Construction Management (OECM) for consultation. Additional
	references are listed in APPENDIX A.
	
3.	APPLICABILITY
	
	To FPDs and other DOE elements, including contractors, for
	which EVMS is required by DOE O 413.3A and contractual
	requirements. Federal Acquisition Regulation (FAR) 52.234-4
	requires compliance with the current version of ANSI/EIA-748
	at the time of contract award.
	
					SECTION II-EVMS
						  
1.	DESCRIPTION
	
	a.	What is an EVMS-
		
		EVMS is an integrated set of policies, procedures, and
		practices to support program and project management as
		a decision enhancing tool and a critical component of
		risk management. An EVMS:
		
		(1)	Effectively integrates a project's work scope,
			cost, and schedule into a single performance
			measurement baseline (PMB).
			
		(2)	Reliably tracks:
			
			(a)	planned value (PV) of work to be performed or
				the budgeted cost for work scheduled (BCWS),
				
			(b)	earned value (EV) of actual work performed or
				the budgeted cost for work performed (BCWP),
				and
				
			(c)	actual cost (AC) of work performed (ACWP).
				
		(3)	Provides performance measures against the PMB.
			
		(4)	Provides means of identifying, reviewing,
			approving, and incorporating changes to the PMB.
			
		(5)	Provides trend analysis and evaluation of
			estimated cost at completion.
			
		(6)	Provides a sound basis for problem identification,
			corrective actions, and management re-planning.
			
	b.	What is the purpose-
		
		EVMS measures actual performance of work scope and the
		associated cost and schedule versus an agreed to
		baseline plan, while using disciplined means of
		baseline change control for documenting any changes to
		the agreed to baseline plan.
		
	c.	Why use it-
		
		EVMS is a best practice and standard adopted by the
		Federal Government and the project management industry.
		DOE O 413.3A, the Office of Management and Budget
		(OMB), and the Federal Acquisition Regulation (FAR)
		require EVMS.
		
		Projects requesting funds are required to provide EVMS
		data as part of the business case per OMB Circular
		A-11.
		
	d.	When is it used-
		
		(1)	EVMS should be implemented as early as possible in
			a project's life cycle.
			
		(2)	By no later than CD-2, the performance baseline
			(PB that includes the contractor's PMB) must cover
			the entire project life cycle, i.e., through CD-4
			or through the near-term baseline for EM cleanup
			projects.
			
		(3)	DOE O 413.3A requires its use for projects with a
			total project cost (TPC) greater than or equal to
			$20M, and its EVMS data be entered into the DOE
			Project Assessment and Reporting System (PARS)
			after CD-2.
			
		(4)	For projects that do not utilize an EVMS, e.g.,
			firm fixed price contracts, an alternative
			performance management system must be described in
			the project execution plan (PEP) that is approved
			by the acquisition executive.
			
	e.	When is certification of an EVMS required-
		
		(1)	DOE O 413.3A requires for projects greater than or
			equal to $20M that the contractor employ an
			ANSI/EIA-748 compliant EVMS by CD-2. The
			contractor's EVMS should be certified as soon as
			possible, but no later than CD-3. In most cases,
			EVMS certification will be a condition for CD-3
			approval. Therefore, efforts need to be made to
			plan and execute the certification process on a
			schedule that can meet this requirement.
			
		(2)	Certification applies to the following:
			
			(a)	projects with a TPC between $20M and $50M
				(DOE O 413.3A requires self-certification by
				the contractor);
				
			(b)	projects with a TPC greater than or equal to
				$50M (DOE O 413.3A requires certification by
				OECM; this does not to preclude contractors
				from obtaining certification by OECM for
				projects with a TPC less than $50M); and
				
			(c)	new contractors who have replaced contractors
				with certified EVMS or who require
				certification.
				
		(3)	The certification process should be scheduled in
			advance in anticipation of referenced CDs and new
			contractors.
			
	f.	What are the criteria-
		
		(1)	EVMS needs to comply with DOE O 413.3A,
			ANSI/EIA-748, and contractual requirements.
			
		(2)	Additional clarification on ANSI/EIA-748 is
			provided by the National Defense Industrial
			Association (NDIA), Program Management Systems
			Committee (PMSC), Earned Value Management Systems
			Intent Guide.
			
		(3)	Additional references are listed in APPENDIX A.
			
	g.	When should certification be scheduled-
		
		(1)	Contractors and their programs/Program Secretarial
			Officers (PSOs) should determine the level of
			certification required, i.e., not applicable,
			self-certification, or OECM certification; review
			the contractual requirements; and conduct a self-
			evaluation.
			
		(2)	If OECM certification is required, OECM should be
			contacted to coordinate the review schedule.
			
2.	CRITICAL INFORMATION AND SUGGESTED USES
	
	Following are some critical items that FPDs and other DOE
	elements should closely monitor to ensure successful EVMS
	implementation and continued compliance. Refer to APPENDIX B
	for EVMS calculations.
	
	a.	Variances
		
		(1)	Identifies cost, schedule, and estimate at
			completion (EAC) deviations from the PMB and
			should be reviewed to ensure that their causes,
			corrective action plans (CAPs), and impacts to the
			project are clear, meaningful, and attempt to
			recover negative deviations from the plan and
			address reasons for significant positive
			deviations from the plan.
			
		(2)	FPDs should ensure that variances are accurately
			reported for the current month,
			cumulative-to-date, and against the budget at
			completion (BAC) and should monitor the variance
			analysis reports and the effectiveness of
			corrective actions.
			
		(3)	In addressing variances, historical performance
			against the plan must not be erased, unless to
			correct errors, routine accounting adjustments,
			effects of customer or management directed
			changes, or to improve the baseline integrity and
			accuracy of performance measurement data. Together
			with the remaining management reserve (MR) and DOE
			contingency, updated EACs, and other factors, it
			is critical to understand whether a project is in
			danger of exceeding the contract budget base (CBB)
			or the PB.
			
		(4)	Possible cost variance (CV) causes include the
			following
			
			(a)	rate changes (i.e., labor, overhead),
				
			(b)	vendor discounts or price increases,
				
			(c)	quantity discounts,
				
			(d)	material cost changes, and
				
			(e)	requirement changes.
				
		(5)	Possible schedule variance (SV) causes include
			
			(a)	poor baseline schedule (does it reflect
				reality-),
				
			(b)	subcontractor/vendor cannot deliver when
				needed,
				
			(c)	more/less effort than planned,
				
			(d)	insufficient resources (staffing),
				
			(e)	labor disputes/work stoppage,
				
			(f)	resource availability (is it there when I
				need it-), and
				
			(g)	requirement changes.
				
	b.	Indices
		
		(1)	Indices measure how efficiently a project has
			executed the PMB to the present time. They should
			be closely monitored. They are good indicators
			that could predict future performance but they do
			not stand alone (e.g., by themselves they do not
			monitor whether the critical path work is being
			performed as planned).
			
		(2)	Schedule performance index (SPI) indicates how
			much work you have accomplished against the
			planned work. "How am I doing against my plan-"
			Current or cumulative month data should be
			assessed and trended.
			
		(3)	Cost performance index (CPI) indicates how much
			effort you are getting for every dollar spent. "Am
			I getting the best bang for the buck-" Current or
			cumulative month data should be assessed and
			trended.
			
		(4)	Work remaining (WR), budget remaining (BR), and
			estimate to complete (ETC) should be checked to
			assess if adequate resources are available to
			complete the project.
			
		(5)	To complete performance index (TCPI) indicates the
			budget for work remaining versus the estimate for
			work remaining. TCPIBAC indicates the level of
			efficiency that must be achieved for the cost at
			completion to equal the BAC. TCPIEAC indicates the
			level of efficiency that must be achieved for the
			cost at completion to equal the EAC.
			
	c.	Baseline Management
		
		Baseline management is crucial for properly
		documenting, approving, and implementing changes to the
		PMB and for understanding if the project is in danger
		of exceeding the CBB or the PB.
		
3.	TOOLS
	
	Additional tools to better understand the terms and concepts
	are clarified below.
	
	a.	DOE Gold Card
		
		APPENDIX B provides a comprehensive summary of key EVMS
		terms, their interrelationships, and measurement of
		project progress versus the plan. These terms are the
		foundations for reports including contract performance
		reports (CPRs) in APPENDIX C.
		
	b.	Contract Performance Reports
		
		CPRs provide critical information from the contractor
		to their management and DOE about their performance in
		an organized, easy to understand format. CPRs are
		management reports that provide timely, reliable data
		that is used to assess the contractor's current and
		projected performance, to quantify and track known or
		emerging problems, to determine the contractor's
		ability to achieve the PMB, and to assist in decision
		making. It is important that the CPR be as accurate as
		possible so it may be used for its intended purpose,
		which is to facilitate informed, timely decisions.
		
		CPRs are provided monthly and pertain to all authorized
		work including priced and unpriced efforts.
		
		FAR 34.201(c) requires the contracting officer to
		require contractors to submit EVMS monthly reports for
		those contracts for which EVMS applies. The contract
		requirements should be consulted.
		
		APPENDIX C provides five CPR formats. These formats are
		not required by DOE. If used, they should be tailored
		to meet the needs of the project. When viewed in total
		and over a period of time, these formats can provide
		significant insight regarding project performance. The
		following are the five CPR formats:
		
		(1)	Format 1: WBS
			
		(2)	Format 2: Organizational Categories
			
		(3)	Format 3: Baseline
			
		(4)	Format 4: Staffing
			
		(5)	Format 5: Explanation and Problem Analyses
			
	c.	CPR Checklist
		
		APPENDIX D provides a checklist of items for the FPD to
		review to ensure that CPR formats 1 to 5 are properly
		prepared.
		
	d.	PARS
		
		The following information should be entered into PARS,
		as applicable.
		
		(1)	Complete PV or BCWS profile.
			
		(2)	Monthly EV or BCWP and AC or ACWP. PARS
			automatically calculates the monthly and
			cumulative indices.
			
		(3)	Variance analysis and monthly status reports.
			
		(4)	Latest revised estimate(LRE).
			
		(5)	Contingency remaining.
			
		(6)	Updates of other data fields, i.e., FPD,
			contractor project manager, project description,
			etc.
			
						  
						  
	   SECTION III-CERTIFICATION OF A CONTRACTOR'S EVMS
						  
1.	WHAT CERTIFICATION MEANS
	
	Certification is a process that involves reviewing and
	certifying that the design and implementation of a
	contractor's EVMS is in conformance with ANSI/EIA-748
	primarily for DOE O 413.3A projects. The certification is
	not to verify how well projects or the programs are doing,
	but to assess the capability of the system to provide an
	objective measure of progress and the effective use of the
	system by the contractor and for the Department. Project
	data are simply means of demonstrating EVMS compliance.
	Elements of the EVMS (i.e., the design as reflected by
	policies, procedures, and processes; and the
	implementation as reflected by reports and other
	documents) are evaluated individually and as a whole to
	ensure that they meet the intent of ANSI/EIA-748.
	
2.	CERTIFICATION REVIEW SCOPE
	
	Certification review scope encompasses a project's
	statement of work as reflected by a project specific
	contract and/or PEP.
	
	a.	When a contractor has multiple projects,
		certification may be accomplished on a single or
		multiple project basis, with this decision being
		dependent primarily on the types of projects being
		managed and where each project is in its life cycle.
		
	b.	An overriding objective in making this decision is to
		ensure that the review is conducted using data from
		projects that are sufficiently mature and provide a
		representative sampling of the contractor's total
		efforts to implement an ANSI/EIA-748 compliant EVMS.
		
3.	SELF-CERTIFICATION
	
	a.	DOE line management oversight of the self-
		certification is preferred as the means to gain
		confidence in the contractor's EVMS implementation.
		
	b.	In addition to providing the standard and basis by
		which an EVMS is to be certified, ANSI/EIA-748
		section 5.1 provides the following methods of self-
		evaluation that may be used as basis for
		self-certification. It is recommended that all
		methods be utilized;
		
		(1)	contractor's internal resources,
			
		(2)	a peer group from the contractor's internal
			resources and/or other organizations,
			
		(3)	an outside organization to assist with
			evaluation, and
			
		(4)	associated DOE program representatives to assist
			with evaluation.
			
	c.	Once self-certified, the primary program/PSO should
		formally notify OECM of the self-certification.
		
4.	OECM CERTIFICATION PROCESS
	
	a.	Points of Contact
		
		The following points of contact (POCs) should be
		involved with the certification process.
		
		(1)	OECM EVMS Lead should -
			
			(a)	Serve as primary certification POC.
				
			(b)	Develop the EVMS certification review
				schedule milestones by working with the
				contractor and program/PSO.
				
			(c)	Lead the OECM on-site review team and
				coordinates the review team.
				
		(2)	Contractor POC should -
			
			(a)	Typically be the head of the project
				controls department.
				
			(b)	Assess contract to determine if contractor
				requires OECM certification. If so,
				consults with the program/POC and the
				FPD/site office, to schedule certification.
				
			(c)	Ensure that contractor has a mature EVMS
				supported by its project controls
				department.
				
		(3)	Program/PSO POC should -
			
			(a)	Assess project CD status to determine if
				contractor requires OECM certification. If
				so, contact OECM, in consultation with the
				contractor and FPD/site office, to schedule
				certification with those projects planned
				to be provided as certification review
				documentation.
				
			(b)	Assist in the scheduling the contractor and
				FPD/site office resources to support the
				review efforts.
				
			(c)	Assess contract status to determine if new
				contractor is anticipated. If so, contacts
				OECM, in consultation with the contractor
				and the FPD/site office, to determine if
				certification should be scheduled.
				
		(4)	FPD/Site Office should -
			
			(a)	Assess project CD status to determine if
				contractor requires OECM certification. If
				so, contacts appropriate program/PSO, in
				consultation with the contractor, to
				schedule certification with those projects
				planned to be provided as certification
				review documentation.
				
			(b)	Assess contract status to determine if new
				contractor is anticipated. If so, contacts
				appropriate program/PSO, in consultation
				with the contractor and other site office
				personnel, to determine if certification
				should be scheduled.
				
	b.	Milestones
		
		This section provides a high-level overview of the
		following major milestones of the OECM administered
		EVMS certification process.
		
		(1)	M01-Readiness Assessment (RA)
			
		(2)	M02-On-Site Review
			
		(3)	M03-CAP Analysis & Acceptance
			
		(4)	M04-CAP Implementation and Follow-Up Review
			
		(5)	M05-Certification
			
	c.	M01-Readiness Assessment
		
		(1)	The RA is an on-site meeting with the contractor
			to ensure that the contractor is ready for an
			EVMS certification review. It should be
			approximately one day or longer and scheduled
			two or more months prior to the on-site review.
			The contractor should have conducted some form
			of self-certification prior to the RA. The
			on-site review may be postponed based on the RA
			or failure to address critical issues identified
			in OECM's RA report.
			
		(2)	The RA primarily consists of discussion of the
			general scope of the projects for which a review
			of the EVMS is conducted; the purpose, scope,
			and requirements of the certification review
			including DOE expectations; the on-site review
			process including required documents, interview
			schedule, timeframe for the on-site review, and
			all administrative support needed to conduct a
			quality review; and comments to certification
			review documentation provided by the contractor.
			
		(3)	Deliverables
			
			(a)	Certification Review Documentation-The
				contractor should provide OECM
				certification review documentation
				(APPENDIX E) approximately 30 working days
				prior to the RA.
				
			(b)	RA Report-OECM should provide the contractor,
				program/PSO, and FPD/site office with a
				report of the RA approximately 5 working days
				after the RA.
				
	d.	M02-On-Site Review
		
		(1)	The on-site review with the contractor is to
			assess compliance with ANSI/EIA-748. It should be
			approximately 5 working days.
			
		(2)	The on-site review primarily consists of
			interviews by the OECM on-site certification
			review team (APPENDIX F) of the contractor's
			control account managers (CAM), functional
			managers, and senior managers and of data traces
			to determine if they support the certification
			review documentation.
			
		(3)	At the end of the on-site review, the review
			team should provide an out-brief. The goal is to
			identify all findings. A finding is documented
			in the form of a corrective action request
			(CAR). Other issues may be documented in the
			form of a continuous improvement opportunity
			(CIO).
			
			(a)	A CAR is a systemic or limited occurrence of
				an ANSI/EIA-748 non-compliance or a
				significant impact to reporting, and requires
				a CAP.
				
			(b)	A CIO is a recommended improvement or
				expansion of good practices for wider
				application and does not require a CAP.
				
		(4)	It is critical for the contractor to inform OECM
			of any changes to the EVMS after the on-site
			in-brief.
			
		(5)	Deliverables
			
			(a)	Certification Review Documentation-The
				contractor should provide OECM certification
				review documentation (APPENDIX E)
				approximately 40 working days prior to the
				on-site review.
				
			(b)	On-Site Review Report-OECM should provide the
				contractor, program/PSO, and FPD/site office
				a report of the on-site review with the CARs
				and CIOs approximately 5 working days after
				the on-site out-brief.
				
	e.	M03-CAP Analysis and Acceptance
		
		(1)	Based on the CARs, the contractor should prepare
			and submit a CAP for each CAR. A CAP represents
			the proposed action to address the CAR. A CAP
			clearly documents assumptions and constraints.
			Failure to provide a CAP for each CAR within 60
			working days of the on-site review out-brief may
			result in a new certification review.
			
		(2)	If OECM's CAP analysis concludes that the CAP
			logically outlines in sufficient detail the
			proposal to remedy the ANSI/EIA-748 non-compliance
			or a significant impact to reporting, OECM may
			accept the CAP.
			
		(3)	It may take more than one CAP submission before
			OECM accepts the CAP.
			
		(4)	The contractor is cautioned about implementing
			CAPs prior to OECM's acceptance for it may result
			in the need for even further changes and thereby
			be non-productive.
			
		(5)	Deliverables
			
			(a)	CAP-The contractor should provide OECM CAP
				for each CAR approximately 20 working days
				after the on-site review out-brief.
				
			(b)	CAP Acceptance-OECM should respond to the
				contractor regarding the acceptability of the
				CAP approximately 10 working days after the
				receipt of the CAP.
				
	f.	M04-CAP Implementation and Followup Review
		
		(1)	Based on OECM acceptance of the CAP, the
			contractor should implement the CAP immediately.
			At a minimum, the EVMS description should be
			updated accordingly.
			
		(2)	Concurrently, evidence files (depending on the
			nature of the CARs, a minimum of 3 months of
			supporting documentation including CPRs) of the
			implementation that remedy the CAR should be sent
			to OECM and the follow-up review should be
			coordinated with OECM. Failure to provide
			sufficient evidence files within 5 months of CAP
			acceptance may result in a new certification
			review.
			
		(3)	Upon receipt of all the evidence files, OECM
			should conduct an implementation analysis and
			document the results in the implementation report.
			
		(4)	The implementation report may conclude that the
			CAR
			
			(a)	has not been adequately addressed (resulting
				in another submission of evidence files) or
				
			(b)	has been adequately addressed which
				necessitates coordination of a follow-up
				review.
				
		(5)	Followup Review
			
			(a)	The follow-up review with the contractor is
				to assess compliance with ANSI/EIA-748. It
				should be approximately a one or two day
				on-site review, or OECM may substitute with a
				video conference depending on the complexity
				and the number of CARs, but may involve
				further discussions with the contractor CAMS
				and senior management and on-site review.
				
			(b)	The follow-up review primarily consists of
				interviews of the contractor's CAMs,
				functional managers, and senior managers to
				determine if they support the evidence files
				and close the CARs.
				
			(c)	The follow-up review should result in another
				implementation report which may conclude that
				another submission of evidence files is
				required for EVMS certification. Failure to
				obtain EVMS certification within 6 months of
				on-site review out-brief will result in a new
				certification review assuming OECM promptly
				responds to the contractor's submissions as
				noted.
				
		(6)	Deliverables
			
			(a)	Evidence Files-The contractor should provide
				OECM evidence files approximately 85 working
				days after the on-site review out-brief.
				There should be a set of evidence files for
				each CAP.
				
			(b)	Implementation Report-OECM should provide
				contractor, program/PSO, and FRP/site office
				a report of the implementation analysis
				approximately 20 working days after receipt
				of the evidence files.
				
	g.	M05-Certification
		
		(1)	Based on a successful follow-up review, OECM
			should provide the contractor a letter of
			certification, a significant achievement, with the
			expectation that the contractor maintains its
			EVMS, e.g., conducts surveillance as part of their
			integrated management system and with continuous
			improvement.
			
		(2)	It is expected that an EVMS should be ready for
			certification within six months of the on-site
			review. If the time between the on-site review and
			certification is longer than six months, then
			another on-site review may be necessary. In no
			case, should it extend beyond one year without
			restarting the certification process.
			
			(3)	Deliverables
			
			(a)	Letter of EVMS Certification-OECM should
				provide contractor letter certifying that the
				contractor's EVMS is in compliance with
				ANSI/EIA-748 approximately 10 working days
				after the successful follow-up review.
				
						  
						  
			   SECTION IV-EVMS SURVEILLANCE
						  
Surveillance is the recurring process of reviewing a contractor's
EVMS to ensure continued compliance with ANSI/EIA-748. DOE uses,
as a guide, the NDIA PMSC, Surveillance Guide. An effective
surveillance process ensures that the key elements and the use of
an EVMS are maintained over time and on subsequent applications
(e.g., on new projects). The purpose of surveillance is to ensure
that the contractor is continuing to use their EVMS effectively
to monitor and manage cost, schedule, and technical performance.
Through the process of surveillance, successful practices may be
shared as part of the lessons learned process.

1.	CONTRACTOR SURVEILLANCE
	
	The contractor has the primary responsibility for
	implementing and maintaining a surveillance program to
	ensure continued compliance of the system with ANSI/EIA-748.
	
	An acceptable approach to surveillance planning could begin
	with the establishment of a comprehensive surveillance plan
	prepared by the contractor and provided for information and
	comment to the program/PSO and FPD/site office. The
	surveillance plan includes a clear definition of the scope
	of surveillance, the responsibilities, methods for
	conducting, and the schedule. The plan typically spans
	multiple years, is supplemented by an annual schedule with
	additional detail regarding the planned surveillances, and
	the projects selected for review. Responsibility for EVMS
	surveillance should be within an organization separate from
	the project manager's line management.
	
2.	DOE LINE MANAGEMENT OVERSIGHT
	
	While the contractor has the primary responsibility for EVMS
	surveillance, DOE line management (i.e., the FPD/site office
	up through the program/PSO) also shares in the
	responsibility. DOE line management should assess the
	results of the contractor surveillance program to determine
	if additional DOE-led surveillances are necessary. To this
	end, in reviewing the results of the surveillances, DOE line
	management may decide to initiate program office directed
	surveillances or it may request (through its program office)
	that OECM lead a surveillance review.
	
3.	DOE OECM OVERSIGHT
	
	As part of DOE's continuous effort to institutionalize EVMS
	across the Department and export best business practices
	across programs, OECM will conduct periodic surveillance
	reviews similar to the certification review. Many events,
	such as a request from the field or program office, negative
	performance indicators, and OECM schedules can trigger
	reviews. This does not abrogate the responsibility of the
	contractor and DOE line management to establish their EVMS
	surveillance program. The DOE headquarters surveillance
	program is one of oversight.
	
						  
						  
				SECTION V-LESSONS LEARNED
						  
The EVMS lessons learned contained within this section originate
from CARs and CIOs identified during certification and
surveillance reviews. They may also arise from external
independent reviews (EIRs), independent project reviews (IPRs),
day-to-day execution, and other industry sources. The following
are ten common lessons learned issues that merit discussion.

1.	ACQUISITION PROCESS
	
	The request for proposal should specify what is required
	of the contractor as it relates to EVMS, and should make
	specific reference to ANSI/EIA-748, FAR, and DOE O 413.3A
	contractor requirements.
	
2.	BUDGET VERSUS FUNDS AND PERFORMANCE MEASUREMENT BASELINE
	
	The following basic concepts are often confused and can
	result in non-compliance.
	
	a.	Funds are a monetary resource provided to execute the
		plan.
		
	b.	Budget equates to the plan. The PMB represents the
		performance plan against which the contractor is
		measured as the contractor executes the total, not
		just the annual project scope of work. It is the
		summation of the time-phased budgets for all control
		accounts (CAs), summary level planning packages
		(SLPPs), applicable indirect budgets, and any
		undistributed budget (UB). For traditional projects,
		the PMB at CD-2 is required to encompass the entire
		project scope of work. For environmental management
		cleanup projects (especially long term projects), the
		PMB at CD-2 may be for the contract period, a near-
		term baseline, or the life cycle period. Contractors
		must not zero out past variances within the PMB to
		manage funds. Historical performance against the plan
		must not be erased, unless to correct errors, routine
		accounting adjustments, effects of customer or
		management directed changes, or to improve the
		baseline integrity and accuracy of performance
		measurement data. In other words-
		
		(1)	historical performance against the plan must not
			be erased,
			
		(2)	integrity of the PMB must be maintained, and
			
		(3)	separate means must be employed for funds control.
			
		A fully implemented EVMS is concerned with the total
		project scope, the associated planned budget and
		schedule, and the resultant PMB that is used for
		purposes of measuring progress for the total project
		and is not focused on the management and control of an
		annual funding plan.
		
3.	MANAGEMENT RESERVE
	
	Contractors should be encouraged to establish a challenging
	PMB. However, it must be understood that there will be risk
	events within the contractor's defined scope of work. A
	proper balance of challenge versus risks and managing risks
	can be the key to project success. Many of these risk events
	may happen and the contractor should be allowed to have a
	budget reserve that they can use to better plan future work.
	This budget reserve or MR should not be used to budget newly
	directed work scope.
	
4.	DOE CONTINGENCY
	
	In establishing the TPC, DOE should account for technical
	and programmatic risks. It is important to account for these
	technical and programmatic risks by establishing a DOE
	contingency which would be used for providing additional
	budget should the need arise.
	
5.	CHANGE CONTROL
	
	a.	Many CARs are related to change control - primarily PMB
		maintenance and how MR and DOE contingency are used. It
		is important for the change control process to provide
		visibility to the type of change (e.g., scope change,
		versus a contractor initiated re-plan of future work)
		and that budget has been taken from the appropriate
		account (i.e., MR or DOE contingency). This is
		essential to ensure that the total project scope, cost,
		and schedule are managed by DOE and the contractor.
		
	b.	ANSI/EIA-748 requires that work be performed against a
		planned budget. Therefore, if there is a large proposed
		scope change for which a significant amount of time is
		required prior to DOE approval, mechanisms should exist
		to provide "a not to exceed budget" while contract
		negotiations continue to resolve the final outcome.
		
	c.	Although the issue of budget control (which is a part
		of baseline change control) and funds control are often
		inter-related, the contractor EVMS description and
		implementing procedures oftentimes use the terms
		interchangeably, when in fact they are two separate
		processes.
		
	d.	When describing a baseline change, the total project
		cost and schedule impacts need to be addressed up
		through CD-4 and not just the cost and schedule impacts
		to the annual work plan, or the current project phase
		(e.g., design phase).
		
6.	ESTIMATE AT COMPLETION
	
	Whereas the PMB is important to measure a contractor's
	performance against a plan, an EAC is necessary to
	understand what the anticipated total funding requirements
	are to complete the project. Although most contractors have
	a process for identifying the development of trends and
	revising specific CA EACs to address individual issues,
	oftentimes there is no defined frequency for the development
	of a revised bottoms-up EAC. Real-time updates of EAC at
	individual CA is important, and individual changes are often
	non-linear (i.e., their algebraic sum may not reflect the
	total impact). To better understand the EAC, a bottoms-up
	EAC should be required on some defined frequency. An annual
	update is usually adequate.
	
7.	WORK AUTHORIZATION PROCESS
	
	Usually the contract or PEP captures the total scope of
	work, cost, and schedule. The contractor's work
	authorization process for individual CAs should be recorded
	in an authorizing document from the contractor's line
	management (e.g., project manager) to each CAM. Oftentimes,
	what is documented is an annual work plan and not the total
	project plan.
	
8.	ACCRUALS
	
	Methods for planning, taking credit for actual work
	performed, and accounting for actual costs (pending receipt
	of an invoice) should be synchronized. Disciplined methods
	for reversing accruals (upon receipt of the invoice) should
	be implemented. If they are not, the reported variances may
	not represent actual variances. Additionally, it can lead to
	a significant waste of personnel resources to explain the
	variances.
	
9.	EARNED VALUE TECHNIQUES
	
	Wherever practicable, objective measures (rather than
	management judgment) should be used to take credit for work
	performed. Caution should be exercised when there is a high
	proportion of "level of effort" work in that, for this
	method, the work performed always equals what was planned
	and by itself it never generates a schedule variance.
	Further guidance regarding acceptable earned value
	measurement techniques can be found in the ANSI/EIA-748.
	
10.  OVER-RELIANCE ON CUMULATIVE SPI
	
	In addition to the potential masking of schedule problems
	encountered for projects with a high proportion of "level of
	effort" work, cumulative SPI is not a good indication of
	what is happening on the project critical path and does not
	reflect whether the critical path work is or is not being
	accomplished. In analyzing data, therefore, it is important
	for both the FPD and contractor to analyze more than just
	the cumulative indices. For example, understanding exactly
	what work is on the critical path, and then assessing the
	SPI for each of these work elements would be more
	meaningful.
	
				  APPENDIX A-REFERENCES
						  
	ANSI/EIA-748-A-1998, Earned Value Management Systems, 1998,
	http://ansi.org/.
 
	ANSI/EIA-748-B-2007, Earned Value Management Systems, 2007,
	http://ansi.org/.
 
	DoD EVMS website, http://www.acq.osd.mil/pm.
 
	DoD DI-MGMT-81466A, Contract Performance Report,
	http://www.assistdocs.com/search/document_details.cfm-ident_num
	ber=206421&StartRow=1&PaginatorPageNumber=1&doc%5Fid=DI%
	2DMGMT%2D81466A&status%5Fall=ON&search%5Fmethod=BASIC.
 
	DOE O 413.3A, Program and Project Management for the
	Acquisition of Capital Assets, dated 7-28-06,
	http://management.energy.gov/policy_guidance/project_managment.
	htm.
 
	DOE 413.3 series guides.
 
	FAR Subparts 34.2 and 52.234, Earned Value Management System,
	2008, http://www.acqnet.gov/far/index.html - Provides EVMS and
	certification requirements and solicitation provisions and
	contract clauses for acquisitions.
 
	GAO-07-1134SP, Cost Assessment Guide - Best Practices for
	Estimating and Managing Program Costs, exposure draft, 2007,
	http://www.gao.gov/new.items/d071134sp.pdf.
 
	NDIA PMSC, Earned Value Management Systems Intent Guide, 2006,
	http://www.ndia.org/Template.cfm-Section=Procurement&Template=/
	ContentManagement/ContentDisplay.cfm&ContentID=2310.
 
	NDIA PMSC, Surveillance Guide, 2004,
	http://www.ndia.org/Template.cfm-Section=Procurement&Template=/
	ContentManagement/ContentDisplay.cfm&ContentID=2310.
 
	OMB Circular A-11, Part 7, Planning, Budgeting, Acquisition,
	and Management of Capital Assets, includes supplement, Capital
	Planning Guide, 2007, http://www.whitehouse.gov/omb/circulars/
	a11/current_year/a11_toc.html.
 
	Project Assessment and Reporting System (PARS),
	https://pars.energy.gov.
 
					
			   APPENDIX B-DOE EVMS GOLD CARD

				SEE THE GRAPHIC IN THE PDF


		    APPENDIX C-CPR FORMATS 1 TO 5 OVERVIEW
						   
1.	The following CPR formats are available from the DoD website
	(APPENDIX A). Blank forms are attached on the following
	pages.
	
	a.	Format 1: WBS
		
	Provides data to measure cost and schedule performance by
	product-oriented work breakdown structure (WBS) elements, the
	hardware, software, and services the Government is buying.
	Identifyes any reprogramming adjustment, BAC, EAC, MR, UB,
	and variance at completion by element. It can also show the
	indirect costs by element.
	
	b.	Format 2: Organizational Categories
		
	Provides format 1 data by the contractor's organization
	(functional or integrated product team structure). Refers to
	the organizational categories that reflect the contractor's
	internal management. A certified EVMS requires reporting by
	WBS and organizational breakdown structure (OBS).
	
	c.	Format 3: Baseline
		
	Provides the budget baseline plan against which performance
	is measured.
	
	d.	Format 4: Staffing
		
	Provides staffing forecasts for correlation with the budget
	plan and cost estimates.
	
	e.	Format 5: Explanation and Problem Analyses
		
	A narrative report used to explain significant cost and
	schedule variances and other identified contract problems and
	topics to the CA level.
	
2.	Regarding completion of the data blocks in CPR formats 1 to
	5, many of the blocks are self-explanatory. Sample
	descriptions of some that many not be so clear are provided
	below, and detailed instructions for completing the CPR data
	blocks can be obtained from the DoD website (APPENDIX A).
	
	a.	Phase: Refers to current segment of a project (e.g.,
		design, construction, commissioning).
		
	b.	Share Ratio: Refers to contracts wherein there is a
		sharing of costs, or cost savings, for completion of the
		project above, or below, a contractually established
		target cost. For example, if for every dollar that the
		project is completed less than the target cost the DOE
		retains 80 cents and the contractor's fee is increased
		by 20 cents, then the share ratio would be 80/20.
		
	c.	Cost of Money: Refers to interest costs incurred by the
		contractor when he is financing facility capital assets
		(e.g., the building, equipment procurements, etc). This
		usually is not done for DOE projects (and is usually not
		applicable).
		
3.	CPR FORMATS 1 TO 5

			SEE GRAPHICS IN THE PDF


		APPENDIX D—CPR FORMATS 1 TO 5 CHECKLIST

The following are some checks for CPR formats 1 to 5 noted in APPENDIX C.

1.	FORMAT 1:	WBS

	a.	Check Summary information for correctness (i.e., contract 
		number/type, program name, report period, and signature).

	b.	Verify negotiated cost tracks to the latest definitized 
		contractual actions. REMEMBER: Cost does not include fee. 
		Ensure that the estimated cost of authorized unpriced work 
		(AUW) reflects contractual actions in-progress and not 
		definitized (e.g., change orders, not-to-exceeds, 
		supplemental agreements, and letter contracts).

	c.	Check and verify the following :

		(1)	Fixed Fee should reconcile to the fixed fee 
			definitized on contract.

		(2)	Award Fee Pool should reconcile to the 
			total definitized award fee negotiated on contract.

		(3)	Award Fee earned should reflect the fee the 
			contractor earned to date. Crosscheck with 
			the contract.

		(4)	Award Fee available should reflect the award 
			fee pool less award fee earned less unearned 
			award fee.

	d.	Check and verify that the:

		(1)	Negotiated Price = Negotiated cost + Fixed fee + 
			Award fee earned + Award fee available

		(2)	Estimated Price = Negotiated price + Estimated 
			cost of authorized unpriced work

	e.	Assess changes to the UB that should be explained in 
		Format 3, and efforts should be made to distribute all UBs 
		well ahead of the planned execution of the work. Look for 
		significant changes in the MR budget. Significant changes 
		in budget should be identified in format 3 and explained 
		in format 5. Any entry in the MR EAC represents MR usage.

2.	FORMAT 2:	ORGANIZATIONAL CATEGORIES

	Verify information against organizational categories.

3.	FORMAT 3:		BASELINE

	a.	Check and verify header information. Cross-check 
		with format 1.

	b.	Note changes to PMB since the last report. Reconcile 
		the end of month PMB BCWS to the BCWS “total” 
		line of format 1.

4.	FORMAT 4:	STAFFING

	Check accuracy of headcount data with control account 
	managers (CAM)/integrated project team (IPT) leads. Note 
	changes in headcount since the last report. Look for major 
	changes, i.e., significant shifts in time-phasing of planned 
	staffing in projected headcount (rule of thumb, >10%). 
	Reconcile the headcount with format 3 data. Check for 
	explanation in the format 5.

5.	FORMAT 5:	EXPLANATION AND PROBLEM ANALYSES

	a.	Refer to SECTION II for a discussion of what the 
		variances and indices may be indicating regarding over-all 
		performance, the reasons for the variances, the adequacy 	
		of corrective action plans, and forecasts of future 
		performance. 

	b.	Also check whether the indicated reasons for 
		variances are within (or outside) the listing of identified 
		risks, and whether proper re-planning of future work has 
`		been done to better plan future work, and whether contractor 
		MR is being properly utilized.

	APPENDIX E—TYPICAL CERTIFICATION REVIEW DOCUMENTATION

1.	READINESS ASSESSMENT
	Typical certification review documentation to be provided 
	to OECM approximately 30 working days prior to the RA:

	a.	primary POCs,

	b.	contract with changes/modifications,

	c.	list of subcontractors with associated scopes of work,

	d.	EVMS description, surveillance plan, and change 
		control procedure and other implementing procedures 
		(i.e., referenced documentation),

	e.	cross reference of the EVMS description to ANSI/EIA-748 
		guidelines (compliance map),

	f.	WBS and WBS dictionary,

	g.	organizational chart and OBS, and

	h.	dollarized responsibility assignment matrix (RAM).

2.	ON-SITE REVIEW

	Typical certification review documentation to be provided to OECM 
	approximately 40 working days prior to the on-site review:

	a.	updated documentation including those listed above and 
		already provided,

	b.	contract performance reports (CPR) for the last 3 consecutive 
		months,

	c.	CAM notebooks (representative sample),

	d.	CA plans (representative sample of contractor’s and 
		subcontractor’s),

	e.	program schedules (contractor’s and subcontractor’s),

	f.	variance analysis reports (representative sample),

	g.	variance analysis corrective action log,

	h.	change control log including executed and pending,

	i.	management reserve and contingency log,

	j.	UB log,

	k.	accounting policies and procedures,

	l.	rationale for projected rates,

	m.	disclosure statement, and

	n.	Defense Contract Audit Agency (DCAA), Inspector 
		General (IG), or other audit reports.

APPENDIX F—OECM ON-SITE CERTIFICATION REVIEW TEAM

1.	TYPICAL REVIEW TEAM

	A typical EVMS on-site certification review team led by OECM is shown in Table 1.
	Table 1 – Typical OECM On-Site Certification Review and Interview Team Matrix

____________________________________________________________________________________ 
4 Functional Teams	4 Interview Teams
_________________________________________________________________________
No.	5 Functional Areas	Member	1	2	3	4
						     (Accounting)
_________________________________________________________________________
A	Organization	Member A1	x			
		Member A2		x		
	Analysis and 
	Management
	 Reports	Member A3			x	

B	Planning and
	Budgeting	Member B1		x		
		Member B2	x			
		Member B3			x	

C	Accounting	Member C1				x
		Member C2				x
		Member C3				x

D	Revisions	Member D1			x	
		Member D2	x			
		Member D3		x		

The 5 functional areas shown represent the 5 process groupings into which the 
32 ANSI/EIA-748 guidelines are categorized. A functional area lead is 
designated for each functional area. Each functional team member is 
assigned to an interview team, wherein the interview teams are 
constructed to have representation from all but team 4, the accounting 
team. The accounting team also conducts interviews, and although it is 
assigned to a few of the interviews conducted by the other three interview 
teams, in large part it conducts its interviews of accounting personnel. In 
addition to the interviews of the contractor personnel conducted by the 
4 interview teams, the OECM EVMS lead with other team members conduct 
interviews of the contractor’s senior management.

2.	FUNCTIONING OF THE REVIEW TEAM

	a.	In general, the review team plans and executes its work 
		prior to, during, and following the on-site review, as follows:

		(1)	Prior to the on-site review, team members 
			review the certification review documentation 
			that is supplied by the OECM EVMS lead to 
			assess compliance of the EVMS processes and 
			procedures with ANSI/EIA-748.

		(2)	During the on-site review, team members 
			conduct interviews and data traces to determine 
			if contractor personnel are doing business 
			consistent with their EVMS procedures. Also, at 
			the end of each day the entire team assembles to 
			discuss potential problem issues. Further, the OECM 
			EVMS lead with other team members meet at the end 
			of each day of interviews with the contractor in order 
			to ensure that there are no misunderstandings in what 
			the review team believes it is observing and to ensure 
			there are no surprises at the on-site review out-brief.

		(3)	Following the on-site review and acceptance of the 
			contractor’s CAP, the OECM EVMS lead and necessary 
			functional team leads assess the acceptability of the 
			contractor CAP and support further reviews to ensure 
			successful CAP implementation.

	b.	Technical accountability (e.g., determining which issues represent 
		non-compliances with ANSI/EIA-748) rests with OECM; 
		however, in most cases a consensus position is usually 
		reached by the entire review team.

	c.	Staffing of the Review Team

		(1)	In general, the accounting team is comprised 
			primarily of personnel from the program that has 
			accounting over-sight responsibility for the contractor 
			being reviewed. This is usually a DOE field services 
			office or DCAA.

		(2)	The remaining review team members should be 
			qualified personnel who have no conflict of interest 
			with the contractor or that contractor’s projects and 
			may include DOE personnel. If requested by the OECM 
			EVMS lead, the program may need to identify some of 
			the review team members approximately 30 working 
			days prior to the start of the on-site review.

		(3)	Staffing of the review team should be identified by 
			approximately 20 working days prior to the start of 
			the on-site review.

			APPENDIX G—ACRONYMS
AC	actual cost
ACWP	actual cost of work performed
ANSI	American National Standards Institute
AUW	authorized unpriced work
BAC	budget at completion
BCWP	budgeted cost for work performed
BCWS	budgeted cost for work scheduled
BR	budget remaining
CA	control account
CAM	control account manager
CAP	corrective action plan
CAR	corrective action request
CBB	contract budget base
CD	critical decision
CIO	continuous improvement opportunity
CPI	cost performance index
CPR	contract performance report
cum	cumulative
CV	cost variance
CPR	contract performance report
DCAA	Defense Contract Audit Agency
DoD	Department of Defense
DOE	Department of Energy
EAC	estimate at completion
ETC	estimate to complete
EIA	Electronic Industries Alliance
EIR	external independent review
EV	earned value
EVMS	earned value management system
FAR	Federal Acquisition Regulation
FPD	federal project director
G	guide
GAO	Government Accountability Office
IG	Inspector General
IPR	independent project review
IPT	integrated project team
LRE	latest revised estimate (at completion)
M	million or milestone
MR	management reserve
NDIA	National Defense Industrial Association
O	order
OBS	organizational breakdown structure
OECM	Office of Engineering and Construction Management
OMB	Office of Management and Budget
PARS	Project Assessment and Reporting System
PB	performance baseline
PEP	project execution plan
PMB	performance measurement baseline
PMSC	Program Management Systems Committee
POC	point of contact
PP	planning package
PSO	Program Secretarial Officer
PV	planned value
RA	readiness assessment
RAM	responsibility assignment matrix
SLPP	summary level planning package
SPI	schedule performance index
SV	schedule variance
TCPI	to complete performance index
TPC	total project cost
UB	undistributed budget
VAC	variance at completion
WBS	work breakdown structure
WP	work package
WR	work remaining