U.S. Department of Energy GUIDE
Washington, D.C. 20585 DOE G 413.3-7
9-16-08
Risk Management Guide
[This Guide describes suggested nonmandatory approaches for
meeting requirements. Guides are not requirements documents and
are not to be construed as requirements in any audit or appraisal
for compliance with the parent Policy, Order, Notice, or Manual.]
FOREWORD
This Department of Energy Guide is for use by all DOE elements.
This Guide intends to provide non-mandatory approaches for
implementing the requirements of DOE O 413.3A, Program and
Project Management for the Acquisition of Capital Assets, dated
7-28-06. Guides are not requirement documents and should not be
construed as requirements. DOE Guides are part of the DOE
Directives System and provide suggested ways of implementing
Orders, Manuals, and other regulatory documents.
1.0 PURPOSE
The purpose of this guide is to describe an effective risk
management process that should lead to successful project
execution. The continuous and iterative process includes updating
project risk documents and the risk management plan and
emphasizes implementation communication of the risks and actions
taken.
This guidance document provides a framework for identifying and
managing key technical, schedule, and cost risks through applying
the requirements of DOE O 413.3A. The Order states that risk
management is an essential element of every project.
Risk management for this purpose is the handling of risks through
specific methods and techniques within the bounds of project
management. The operable definition of risk for this guide is a
factor, element, constraint, or course of action that introduces
an uncertainty of outcome that could impact project objectives.
The risks to be handled are comprised of threats and
opportunities. Threats are risks with negative consequences, and
opportunities are risks with positive benefits.
The risk management process set forth in this guidance
demonstrates a continuous and iterative process. This framework
meets the requirements of the Order to be forward looking,
structured, and informative. Further, the process addresses
within the terms of technical risks the technical uncertainties
required by the Order. The issue of the establishment of design
margins to address the uncertainties or unknowns associated with
the design is addressed in greater detail in the Guide handling
issues of design and construction; however, the nature of the
risk and its uncertainty arising from directed assessments
associated with designs are addressed by this Guide as are the
necessities of increased technical oversight requirements.
Further, this risk management process has been developed to meet
the overall monitoring and reporting requirements, and to allow
one to continue to monitor those technical uncertainties.
2.0 SCOPE
This guide may be used by all Department of Energy (DOE) offices
and the National Nuclear Security Administration (NNSA), their
respective field operations, operations’ contractors, and
subcontractors as specified in their respective contracts.
This guide addresses the overall processes for the initiation,
planning, executing, monitoring, and close out of the risk
management throughout the life cycle of the programs and
projects. The concepts and practices described are considered to
be beneficial to all types of projects and as such the concepts
and practices should be applied to those projects with tailoring
based upon the project complexity, the size and duration of the
project; the initial overall risk determination of the project;
the organizational risk procedures; the available personnel and
their skills levels for performing risk management; and,
available relevant data and its validation.
The final determination for tailoring the level of risk
management rests with the Federal Project Director (FPD) or the
Contractor Project Manager (CPM) as described in the project
execution plan as signed by the acquisition executive or the
contractor project management plan, respectively.
This guidance and advice is intended to meet, but is not limited
to, the following objectives:
• Identify the risk management processes.
• Identify the steps necessary to facilitate the
implementation of those processes.
• Provide life-cycle risk management guidance.
• Provide risk management documentation guidance.
• Provide risk management monitoring and reporting guidance.
This guide is not intended to replace assessment processes
developed for nuclear safety and environmental, safety, health,
and quality (ESH&Q). It is also not intended to replace
assessment processes developed for safeguards and security. This
guidance also recognizes the benefit and necessity of early
consideration and integration of safety related project risk into
the project risk management process.
Methodology
3.0 RISK MANAGEMENT ORGANIZATIONAL STRUCTURE, CONCEPT, AND
RESPONSIBILITIES
3.1 Risk Management Organizational Structure
The formal organizational breakdown structure for risk
management, the same as for the Project Execution Plan or Project
Management Plan, is established by the official organizational
breakdown structures or organizational charts issued by the
program office. Whenever the risk management plan is updated, the
organizational breakdown structure, contained therein, should be
updated as well, if changes have been made to those structures.
The organizational breakdown structure serves three purposes in
risk management. These purposes, as well as illustrations for
each purpose, are shown as follows:
• Highlights the structure for the management framework with
which risk management and the decision processes will
occur.
- Assists with identifying organizational risks.
- Assists with identifying where certain risk management
decision ownership and decision processes reside.
• Illustrates the chain of authority and communication for
risk management decision processes.
- Reduces time for critical risk communication.
- Allows for documentation of risk communication chain.
• Provides a means to map risks organizationally to determine
where organizationally the greatest number of risks resides
and/or the risks with the highest qualitative value reside.
- Can provide a format for the development of a Risk
Breakdown Structure (see Attachment 1, Risk Breakdown
Structure).
- Provides a means of identifying risk owners.
3.2 Risk Management Organizational Concept
Programs and projects are of varied types, often long term, and
of differing complexity. The risks may span multiple levels of
organizational management, crosscut multiple organizations,
and/or crosscut different sites within the complex. For risk
management to be effective, it should be an integral part of the
organization’s corporate enterprises-governance (e.g., standards,
procedures, directives, policies, and other management
documentation).
In order to implement the risk management principles1 and
processes successfully, an organizational process perspective
should be considered within which the risk management processes
could operate. The processes and procedures, along with
applicable tools to be used for performing risk management
functions should be carefully considered, established, and well
defined when implemented. The risk management processes described
later in this guide should be carefully tailored to involve and
meet the needs of the organization’s internal planning,
assessment, project controls, risk monitoring, reporting, and
decision-making processes at the different levels of risk
management.
A clearly defined integrated risk management framework should
consider the structure and interactions of the management
organization(s) and management levels. These should be charted or
mapped out and institutionalized (process-wise), so that they can
be well understood within each organization(s), in order to help:
Align the organization(s) to accomplish the mission, in
concert with the established requirements, policies,
strategic plans, roles and responsibilities aligned via
clearly defined and well-understood processes and
procedures. This alignment should be done in order to meet
the goals and objectives of the Department at all levels of
the organization(s) supported by risk management-based
decision making knowledge.
Increase the interaction and communication between upper
management and functional contributors, and to better
understand all types of project risks, such as: political,
economic, social, and technological, policy, program,
project, financial, resource-based, health and safety,
safeguards and security, and operational. Without this
interaction, identification of risks and the communication
and handling of risks cannot be adequately accomplished, or
be well understood.
Apply a consistent integrated systematic risk management
process approach at all levels of risk management to support
decision-making and encourage better understanding and
application of the risk management process. For example, the
same risk can exist in different organizational levels such
as the contractor, the site DOE Offices, and Program
Headquarters (HQ) Offices. This risk will be shared by all
of the organizations but from different perspectives. These
risks can crosscut and affect capital, cleanup, information
technology, or operating projects, etc.
Build a cultural environment that fosters risk management
related learning, innovation, due diligence, responsible
leadership, management participation and involvement,
lessons learned, continuous improvement, and successive
knowledge transfer.
The risk management framework should be completely integrated
into the procedures and processes of the organization. The risk
management processes and procedures should be supported by
management through self-assessments, lessons learned, and a
continuous improvement environment.
3.3 Risk Management Organizational Responsibilities
The key roles, roles which have a deterministic impact upon the
risk management of the project, and responsibilities are the
highest level of project risk authority and responsibility. A
complete responsibility assignment matrix for risk management
roles and responsibilities should be included in the risk
management plan.
3.3.1 Federal Project Director
Throughout the project life cycle, the FPD, in order to manage
risks regarding government supplied materials and information as
well as federally-owned project risks and those mission related
risks that must be managed at the site location, should:
• Apply a continuous, iterative risk management process.
• Document and manage risks.
• Develop, maintain, and provide required risk documentation,
and reporting to appropriate project and program management
personnel. This includes providing configuration management
for this documentation.
• Ensure a tailored approach to risk management.
• Inform the Acquisition Executive and the sponsoring program
office of all major risks as soon as they are recognized.
• Formally accept or reject any risks that are proposed to be
transferred from the contractor to the federal government
(DOE or NNSA).
• Verify acceptance and closure of key program/project risks.
3.3.2 Integrated Project Team
Throughout the project life cycle, the Integrated Project Team
(IPT), in support of the FPD, should:
• Apply the continuous risk management process.
• Document and manage the risk management process contained
within the risk management plan and the risk management
communication plan (see Section 5.3, Risk Management
Communication Plan).
• Provide documentation and management of risks throughout
the program/project life cycle via the program/project risk
register (see Section 4.3.5, Risk Register, and Attachment
1, Risk Breakdown Structure).
• Develop and provide the program/project risk status report
(see Attachment 2, Risk Status Report) to management.
• Concur through consensus as to the key program/project
identified risks for the project life cycle.
3.3.3 Contractor Project Manager
The risk management responsibilities of the CPM, unless otherwise
directed by the contract terms and conditions as they bound the
project life cycle, should be to:
• Apply a continuous, iterative risk management process.
• Document and manage risks.
• Develop, maintain, and provide required risk documentation
and reporting and configuration management to appropriate
project and program management personnel. This includes
providing configuration management for this documentation.
• Ensure a tailored approach to risk management.
• Verify acceptance and closure of key program/project risks.
3.3.4 DOE/National Nuclear Security Administration Headquarters
Headquarters program office personnel should:
• Provide guidance on the risk management process.
• Provide support to site office programs in the evaluation,
analysis, assessment, and reporting of risk.
• Provide support to site office programs for training and
education in risk management.
• Facilitate information sharing on risk management best
practices, trends, and publications.
• Interface with the FPD and IPT for risk.
4.0 RISK MANAGEMENT PROCESS WITHIN THE PROJECT LIFE CYCLE
4.1 Project Phase Integration
This risk management guide is integrated with DOE O 413.3A, but
it also suggests process steps beyond those stated in DOE O
413.3A in some specific instances, such as the Risk Register. The
risk management process as integrated with DOE O 413.3A is a
continuous, iterative process that is performed throughout the
project life cycle from initiation through project closeout.
Wherever possible, the project phases in DOE O 413.3A should be
aligned with the risk management process to allow an integrated
view (Figure 1). Figure 1 provides a view of the steps of the
risk management process against the Critical Decision Phases of a
project. While this view presents a static view of risk
management, it is not meant to infer that the process is static.
Instead it is meant to demonstrate when one should initiate for
the first time certain process steps.
The risk management plan should be included in or referenced in
the preliminary project execution plan during CD-1 (see Section
5.2, Risk Management Plan).
See the figure in the PDF
Figure 1. Critical Decision Phases with Continuous and Iterative
Risk Management
While the process flow appears linear, the process itself is
iterative and not necessarily consecutive. The risk-planning
step, for example, is continuous throughout the project life
cycle, as is the need for risk communication and documentation.
The pattern that is represented by the linear process diagram
(Figure 2) demonstrates that certain steps generally precede
others; however, as the project proceeds, the review processes do
not necessarily progress in the same manner.
See the figure in the PDF
Figure 2. Risk Management Process. Linear Representation
of the Continuous and Iterative Process
4.2 Risk Planning
The risk planning process should begin in the early stages of the
project, before CD-0, or the Initiation/Definition Phases.
Planning sets the stage and tone for risk management and involves
many critical initial decisions that should be documented and
organized for interactive strategy development.
Risk planning is conducted by the IPT (if assembled by this time)
and a FPD or an assigned federal employee. Risk planning should
establish methods to manage risks, including affirming the
scales, metrics, and other mechanisms or determining and
documenting modifications to those scales, metrics, and
mechanisms. A communication structure should be developed to use
until it can be determined whether a formal federal risk
management communication plan should be written and executed as
part of the tailoring decisions to be made in regard to the
project (see Section 6.0, Tailoring of Risk Management). Input to
the planning process includes the project objectives,
assumptions, mission need statement, customer/stakeholder
expectations, and site office risk management policies and
practices.
The IPT (if assembled by this time) and a FPD, or an assigned
federal employee should establish a budget for risk management
during the project’s next phase. The team should also establish
what resources, both human and material, would be required for
successful risk management on the project. Further, an initial
reporting structure and documentation format should also be
established for the project.
Overall objectives for risk planning are:
• Establish the overall risk nature of the project including
recognizing the relative importance of the project to the
office with the DOE or the NNSA (to include its priority
ranking within the organization).
• Establish the overall experience and project knowledge of
the IPT.
• Establish the technical background and risk knowledge of
the IPT.
• Establish the overall level of project risk.
An initial responsibility assignment matrix with roles and
responsibilities for various risk management tasks should be
developed (see Attachment 3, Risk Responsibility Assignment
Matrix). Through this Responsibility Assignment Matrix, gaps in
expertise should be identified and plans to acquire that
expertise should be developed.
The result of the risk planning process is the risk management
plan (see Section 5.2, Risk Management Plan). This risk
management plan is the roadmap that tells the government or
contractor team how to proceed in risk management from where the
project is conceptually to where the project is predicted to be
in the future based upon initial risk management project planning
documentation.
4.3 Risk Assessment
Risk assessment includes the overall processes of risk
identification and analysis. The risk assessment process provides
the IPT the definition of risk for the project by identifying,
analyzing, and quantifying potential program and project risks in
terms of probability and consequences. Risk analysis is a
technical and systematic process that is designed to examine
risks, identify assumptions regarding those risks, identify
potential causes for those risks, and determine any relationships
to other identified risks, as well as stating the overall risk
factor in terms of the probability and consequence, if the risk
should occur. Risk identification and analysis are performed
sequentially with identification being the first step (see
Attachment 5, Risk Register).
4.3.1 Risk Identification
As with each step in the risk management process, risk
identification should be done continuously throughout the project
life cycle. As a project changes—particularly in terms of budget,
schedule, or scope—or when a mandatory review or update is
required, the risk identification process should be iterated, at
least in part. Prior to a major project review, a review of the
risk identification process should be done to ensure the process
is complete and no portion should be redone.
To begin risk identification, the IPT should attempt to break the
project elements into a risk breakdown structure that is the
hierarchical structuring of risks. The risk breakdown structure
is a structured and organized method to present the project risks
and to allow for an understanding of those risks in one or more
hierarchical manners to demonstrate the most likely source of the
risk. The risk breakdown structure provides an organized list of
risks that represents a coherent portrayal of project risk and
lends itself to a broader risk analysis. The upper levels of the
structure can be set to project, technical, external, and
internal risks; the second tier can be set to cost, schedule, and
scope. Each tier can be broken down further as it makes sense for
the project and lends itself to the next step of risk analysis.
To be useful, the risk breakdown structure should have at least
three tiers.
Such a breakdown is just one methodology, as the type of project
or project organization may dictate the best risk breakdown
structure to apply. Templates for project types may be found in
the literature for software projects, construction projects, and
others; however, these templates should be modified based upon
the specifics of the project being undertaken. The reason for
this statement is that the taxonomy to be used is often project
specific and scope dependent (see Attachment 1, Risk Breakdown
Structure).
Whenever using the Risk Breakdown Structure, it is important to
remember to consider the use of a category called “other.” This
category will promote further brainstorming during the process
and provide another opportunity for risk identification.
The risk breakdown structure can be used with other materials as
the project matures for risk identification as inputs to the
process such as:
• Initial elements of the risk management plan.
• Work breakdown structure.
• Cost estimates.
• Key planning assumptions.
• Mission need statement.
• Preliminary schedules.
• Acquisition strategy documents.
• Technology readiness level information.
• Projects subject to DOE-STD-1189-2008.
• Safety analysis assumptions.
• Safeguards and security analysis assumptions.
• Requirements documents or databases.
• Subject matter expert interviews.
• Stakeholder input.
• Designs or specifications.
• Historical records.
• Lessons learned.
• Any legislative language pertaining to the project.
• Other similar projects.
• Pertinent published material.
Various techniques that can be used to elicit risks include
brainstorming, interviews and diagram techniques. Regardless of
the technique, the result should not be limiting and should
involve the greatest number of knowledgeable participants that
the IPT can accommodate within their constraints. Once the
process of initial risk identification has been complete, the IPT
should follow up with the self-assessment process noted in
Section 4.7.2.2, Self Assessment, using the Risk Identification
Checklist in Attachment 8.
As the team identifies risks, it is important that they are aware
of biases that may influence the information. Typical biases the
facilitator of the risk identification should be aware include
the following:
• Status quo—strong bias toward alternatives that perpetuate
current direction.
• Confirming evidence bias—information that supports existing
points of view are championed while avoiding information
that contradicts.
• Anchoring—disproportionate weight is given to the first
information provided.
• Sunk cost—tend to make choices in a way that justify past
choices, unwillingness to change direction.
When identifying a risk, it should be stated clearly in terms of
both the risk event and the consequences to the project/program.
The format for the risk identified should generally be
cause/risk/effect.
One may choose to record cause, risk, and effect in separate
fields to facilitate grouping of risks into categories based on
commonality of these attributes.
This format should be employed whether the risk is a threat to
the project or an opportunity, which is a risk with a benefit.
Documentation should be done in affirmative terms—as if the risk
will occur—to enable the IPT to draft a definitive risk handling
strategy. The information should be captured in a risk register,
a database designed to capture all necessary information about a
risk and facilitate tracking and reporting (see Attachment 1,
Risk Breakdown Structure).
Examples of risks captured in the affirmative are:
• Discovery of classified material in landfill delays removal
of transuranic material and impacts schedule.
• Delay in signing a cooperative research and development
agreement impacts availability of specialized research
personnel in statistical analysis of nano-scale stress
analysis of carbon-based metals delaying project by one
year.
• Seismic site analysis area is expanded due to adjacent
construction site seismic reports resulting in new drilling
and reporting delaying site preparation by six months.
Risks should be stated as separate items and should not be
grouped or bundled. As an example, one should identify each
material handling risk for a process separately and not as
material handling risks. One should also be aware that an
opportunity will also have one or more threats which should be
identified as a separate risk item in the register. It is helpful
to link the items either by Work Breakdown Structure
identification number or by other unique identification
methodology that will indicate the linkage. The linkage is
important, especially if the risk owner is different as the risk
owners may need to coordinate their efforts on the risk handling
strategies.
The IPT should capture opportunities before threats.
Opportunities are often shared between and among projects. It
should be noted that opportunities for one participant could be
detrimental to another; therefore, they should be worked
cooperatively. Examples of opportunities include:
• Available human resources with flexible scheduling can be
shared to the advantage of two or more projects.
• A crane is available at another site at a lower cost than
purchasing a new or a used one.
• Results of adjacent construction site seismic reports cause
the seismic site analysis area to be expanded, resulting in
new drilling and reporting, and delaying site preparation
by six months.
In addition to identifying a risk in terms of the causal event
and consequence, the pertinent assumptions regarding that risk
should be captured in the risk register to aid in future
reporting of the risk. These assumptions might include items such
as, but not limited to, interfaces among and between sites,
projects, agencies, and other entities; dependencies as human
resources, equipment, facilities, or other; and historically
known items that may impact the project either positively or
negatively. The assumptions should be kept current and should be
validated through various methods including documentation and
subject matter experts.
4.3.2 Assignment of the Risk Owner
Before assigning a qualitative assessment to the dimensions of a
risk (probability and consequence), a risk owner should be
identified. The risk owner is the team member responsible for
dealing with a specified risk, ensuring effective handling
responses or strategies are developed and implemented, as well as
filing appropriate reports on the risk in a timely fashion. The
risk owner should also validate the qualitative and quantitative
assessments assigned to their risk. Finally, the risk owner
should ensure that risk assumptions are captured in the risk
register for future reference and assessment of the risk and to
assist possible risk transfer in the future.
Any action taken in regard to a risk should be validated with the
risk owner before closure on that action can be taken.
4.3.3 Assignment of Probability and Consequence
Risk analysis has two dimensions—probability and consequence.
Probability is the likelihood of an event occurring, expressed as
a qualitative and/or quantitative metric. Consequence is the
outcome of an event. The outcome of an event may include cost
and/or schedule impacts expressed as a qualitative and/or
quantitative metric. The IPT estimates probability and
consequence dimensions (qualitative and quantitative)
subjectively, with the risk owner making the final determination.
During the qualitative analysis, the probability and consequence
scales can be categorical. However, it is often useful to assign
quantitative metrics to the qualitative categories to help ensure
consistent assignment of probabilities and consequences across a
project/program (see Attachment 4, Probability Scale/Schedule
Consequence Criteria). This approach works well for probability
and consequence.
4.3.4 Assignment of Risk Trigger Metrics
A risk trigger metric is an event, occurrence or sequence of
events that indicates that a risk may be about to occur, or the
pre-step for the risk indicating that the risk will be initiated.
The risk trigger metric is assigned to the risk at the time the
risk is identified and entered into the risk register. The
trigger metric is then assigned a date that will allow the risk
owner to monitor the trigger. The purpose of monitoring the
trigger is to allow adequate preparation for the initiation of
the risk handling strategy and to verify that there is adequate
cost and schedule to implement the risk handling strategy.
4.3.5 Risk Register
The risk register is the document or database that is the
information repository for each identified risk. It provides a
common, uniform format for the presentation of risk-related
information regarding the identified risks. The level of detail
may vary depending upon the complexity of the project and the
overall risk level presented by the project as determined
initially at the initiation phase of the project.
The fields stated here are those that should appear in the risk
register, whether the risks presented are a threat or an
opportunity. Other fields that are suggested to be considered are
contained in Attachment 5, Risk Register, and are suggested to be
included as they allow a much better view of the full field of
options available to the FPD and CPM:
• Project title and code (denotes how the project is captured
in the tracking system used by the site office and/or
contractor).
• FPD and CPM.
• Unique risk identifier (determined by the individual site).
• Risk statement.
• Risk category (project, technical, internal, external, and
any sub-category that may be deemed unique to the project
such as safety or environment).
• Risk owner.
• Risk assumptions.
• Probability of risk occurrence and basis.
• Consequence of risk occurrence and basis.
• Trigger event.
• Handling strategy (type and step-wise approach with
metrics, who has the action, planned dates, and actual
completion dates).
• Success metric for overall handling strategy.
• Residual risks.
• Secondary risks.
• Status (open/closed) and basis.
The risk register may also include back-up strategies for primary
risks, risk handling strategies for residual and secondary risks,
the dates of upcoming or previous risk reviews, and a comment
section for historical documentation, lessons learned, and
subject matter experts’ input.
4.3.6 Risk Analysis
Risk analysis from a project management perspective should begin
with the identification of the overall risk level of the project
during the Initiation Phase. This analysis supports the
preparation of the mission need statement and the tailoring
strategy during CD-0.
The review of various approaches to the mission, goals, and
objectives of the project should involve a comparative analysis
of alternatives and overall risk identification, as well as the
analysis for those alternatives. As a general rule, the simplest
analysis that should be performed at CD-0 is a cost and benefit
review, a type of qualitative review. The qualitative approach
involves listing presumed overall costs over presumed costs for
projected benefits. The result would be an overall assessment of
the risk on the project (see Attachment 6, Cost/Benefit Analysis,
for an alternative quantitative approach that can be used when
enough information is available).
After CD-1 approval, two forms of risk analysis may be performed:
Qualitative and quantitative. These analyses serve as the
foundation for continuing dialog about future risk realizations
and the need for the application of the contingency and
management reserve, which are subjects, addressed in other DOE G
413.3-series guides that handle cost and contingency
calculations.
4.3.6.1 Qualitative Risk Analysis
The purpose of qualitative risk analysis is to provide a
comprehensive understanding of known risks for prioritization on
the project. Qualitative risk assessment calls for several risk
characteristics to be estimated:
• Risk probability.
• Risk consequence.
• Trigger metrics or conditions.
The FPD or CPM may decide to include other qualitative
characteristics such as affected project elements, influences on
the risk, and assumptions about the trigger conditions. These
items should be captured in the risk register or risk register
database.
If only a qualitative analysis is to be done, various cost and
schedule factors may be used to provide for contingency and
management reserve calculations. (Note: terminology may vary
depending upon the Program Office to which the program or project
is assigned.)
Qualitative analysis, or assessment as it is sometimes referred,
is the attempt to adequately characterize risk in words so as to
enable the development of an appropriate risk handling strategy.
Additionally, qualitative analysis assigns a risk rating to each
risk, which allows for a risk grouping process to occur. This
grouping of risks permits the FPD and the CPM to discern patterns
of risk on the project. The patterns are indicative of the areas
of risk exposure on the project. The qualitative analysis is also
the foundation for initiating the quantitative risk analysis, if
required.
Qualitative risk analysis should also be performed on residual
risks and secondary risks, but only after the handling strategy
has been determined for the primary risk. Again, the risk owner
should accept the risk ranking.
4.3.6.1.1 Qualitative Matrices Analysis
One of the tools used to assign risk ratings is a qualitative
risk analysis matrix, also referred to as a probability impact
diagram or matrix (see Figure 3, Qualitative Risk Analysis Matrix
for the FPD, and Figure 4, Qualitative Risk Analysis Matrix for
the Contractor Project Manager, for examples). Risk ratings are
also often referred to as risk impact scores.
The matrix combines the probability and consequence of a risk to
identify a risk rating for each individual risk. Each of these
risk ratings represents a judgment as to the relative risk to the
project and categorizes at a minimum, each risk as low, moderate
or high. Based on these risk ratings, key risks, risk handling
strategies, and risk communication strategies can be identified.
Risk consequences for the FPD and the (CPM) in most cases are
different because the FPD is driven more from strategic mission
objectives than contract performance objectives. Mission
objectives are more strategically oriented than corporate or
monetary incentive based. Therefore, two risk matrices are
recommended.
See the table in the PDF
Figure 3. Qualitative Risk Analysis Matrix for the Federal Project Director
See the table in the PDF
Figure 4. Qualitative Risk Analysis Matrix for the Contractor
Project Manager
As with a threat, an opportunity should also be assessed using a
risk assessment framework (see Attachment 7 for an example of an
opportunity matrix). The matrix may be modified to provide one
for the CPM by reviewing the consequences specifically in terms
of the impacts to the contract terms in regard to the project.
The matrix is an option for sites that do not have site specific
or contractor specific matrix or matrices.
A project’s tolerance limit for overall risk rating is referred
to as the risk threshold. The risk owner should accept this
rating or the process should be reiterated to validate the
probability and consequence ratings to obtain acceptance by the
risk owner. This same rating process can be used for
opportunities by changing the terms to positive for the
consequences in the matrices.
Determining the average risk rating can determine the overall
project risk rating. Risk ratings are assigned via a matrix to
the risk, threat or opportunity, based upon the risk
classification. Typical risk classifications are low, moderate,
or high. Another option would be to use numerical values for
ratings. The numerical value can be tailored to the project or
standardized for a program.
If a quantitative analysis is going to be performed, the
qualitative analysis can be used to guide the quantitative
analysis. The lowest rated risks generally do not have a
determinative impact upon the project cost or schedule. Risks
that have a determinative impact upon project cost or schedule
will generally rate towards the higher end of the qualitative
scale. However, for many projects, there may be a weak
correlation between a risk’s determinative impact and the
qualitative risk rating.
Care should be taken when comparing project risk scores of
different projects as the project risk scores are a result of a
subjective process and are prepared by different project teams.
Qualitative risk analysis should also be performed on residual
risks and secondary risks, but only after the handling strategy
has been determined for the primary risk. Again, the risk owner
should accept the risk rating.
As the information is gathered and finalized, the data should be
analyzed for bias and perception errors. While the data will not
be systematically used for a quantitative analysis, it should
still be analyzed and perceptions scrutinized.
Following the completion of the qualitative analysis, one should
do a review of Section 4.3.6.3, Project Learning Analysis.
4.3.6.1.2 Other Qualitative Techniques
One qualitative technique that may be used is to do a search on
the risk register for common causes of risks. If the risks are
written in the format of cause/risk/effect with a field for each,
the search can be made simple. If not, a search on common terms
can be done. By looking for risks with common causes, one can
attempt to find opportunities within the handling responses or
strategies as well as commonalities in monitoring triggers, risk
owners, or other shared items. Further, it may be that changes
can be made to the scope to avoid the risks that were not
apparent when viewing the risks individually.
Another qualitative technique for analyzing risks is to use a
network diagram. Using a network diagram to show what tasks bear
the high and moderate risks and where they exist in regard to the
critical path can be a powerful tool in analyzing how much
contingency should be set aside for the risk to ensure that the
critical path is not impacted or the risk to the critical path is
within a manageable range for the FPD or CPM. The diagram is used
to determine the impact to successor tasks, especially those that
either impact the critical path directly or will have an impact
upon a critical input to the critical path.
The risk breakdown structure methodology provides the option of
demonstrating patterns of risk placement or risk groupings. For
instance, rather than specifying the risk, the risk is captured
as a mark on the grid and grouped together, then cut across with
another matrix technique such as the work breakdown structure or
the cost breakdown structure. (See reference – Hillson, D. A.
(2007), “Understanding risk exposure using multiple hierarchies,”
published as part of 2007 PMI Global Congress EMEA Proceedings –
Budapest).
The risk is mapped to the work breakdown structure element that
would be impacted if it occurred. The pattern that emerges allows
one to either use the assigned expected value score or to count
the number of risks associated with the element. This method
allows attention to be focused on specific areas of risks.
Again, a review of Section 4.3.6.3, Project Learning Analysis,
should be done.
4.3.6.2 Quantitative Risk Analysis
Quantitative risk analysis should be used to estimate the impact
of risks on project cost and schedule. Quantitative risk analysis
is a numerical or more objective analysis of the probability and
consequence of individual risks that also addresses the extent of
the overall project risk through the use of a model. The purpose
of the quantitative risk analysis is to provide budget and
completion date estimates of the effect of the risks on the
project using statistical modeling techniques such as Monte
Carlo, Quasi-Monte Carlo, sensitivity simulations, and other
stochastic methodologies, depending upon the project data. Random
sampling from input ranges of time and cost are used to estimate
the impacts on the project’s critical chain. The simulation
produces a range of possible project outcomes.
Quantitative risk analysis can provide a view of which risks or
groups of risks should receive more focused attention. It allows
a numerical evaluation of risk on the project at a point in time.
The simulations can also assist in projecting the future cost and
schedule of the project, if no other actions are taken, as well
as allow for projections to be run based on options the project
could implement, and thus allows the FPD and/or CPM to engage in
discussions about additional handling strategies that could be
implemented. Quantitative analysis also provides a method for the
FPD and/or CPM to determine the level of cost contingency,
management reserve, schedule contingency, and schedule reserve,
when combined with cost uncertainty calculations, that is
required to complete the project within the level of confidence
required by the DOE or NNSA program office.
In general, quantitative analysis is an attempt to determine how
much combined risk the project contains and where and when that
risk exists to enable the project team to focus the project
resources appropriately. Quantitative risk analysis has in the
past been reserved for multi-year, large, and/or complex projects
or projects where the program or executive management desires a
more informed decision as to the amount of risk that exists on
the project. Some DOE offices allow for tailoring with respect to
quantitative risk analysis. The reason for this type of tailoring
is that quantitative analysis allows for the use of different
scenarios and alternatives to the base case. However, for overall
low-risk projects as determined by the qualitative analysis, the
FPD or CPM may determine through the tailoring process and with
the approval of their DOE office, that quantitative analysis is
not warranted.
Quantitative analysis, when done, can be restricted to only those
risks that are ranked higher than low as the overall risk ranking
from the qualitative analysis process. When this is done, the
magnitude of the underestimation should be addressed. The FPD or
CPM may exclude low risks in the analysis at his/her discretion
based upon their project analysis. The critical path for the
project and the approved budget serve as the primary basis for
the risk model and for the project analysis.
It is important to model both risk threats and opportunities. It
is suggested that the two types of risk are modeled separately to
allow for separate analysis given the different project impacts
that the two forms may have.
4.3.6.2.1 Quantifying Probabilities and Impacts for
Quantitative Risk Analysis
A complete and well-executed qualitative analysis is essential to
a quantitative analysis. It will serve as the base for developing
the data for input into the simulation model.
For each risk, a percent is assigned to the probability (how
likely it is the risk will occur), a dollar value distribution is
assigned to the cost impact, and a schedule duration impact is
assigned to the affected activity in the schedule. Depending upon
the software program being used, the percent may need to be
within a specified range. For some projects, especially large
projects, the use of the expected value, a probability weighted
average of all possible outcomes, is a tool which can be used to
determine which risks should receive more attention or more
resources for implementing the risk handling strategies. In
general the concept is implemented as:
EV = P x CI,
where, EV = Expected Value
P = Probability
CI = Cost Impact
Inputs for the calculation include, but not limited to:
• Risk management plan.
• Historical records (especially where similar risks were
handled).
- Actual costs.
- Time impact.
• Subject matter experts.
- Delphi techniques.
- Interviewing staff, crafts, retirees, and others
familiar with similar work efforts at the site or other
sites.
• Technical records such as safety analysis documents
including the risk and opportunity assessment, quality
assessments, safeguards and security analyses, and
environmental assessments.
As information is gathered and finalized, it should be reviewed
for bias and perception errors. These findings should be captured
in the analysis that accompanies the Monte Carlo simulations.
Another item that should be considered in this analysis is a
review of any constraints that may impact the cost and schedule
ranges assigned to the risks. While some of the constraints may
be hard to measure, they should still be captured, for
significant risks, in the text of the analysis so the FPD and the
CPM can take them into consideration as they make decisions
regarding the future handling of the risks and any contingency
requests or management reserve applications.
The inputs into a Monte Carlo simulation process are continuous
probability distributions. The most common methodology is to use
a three-pronged approach from the input enumerated. The input is
the optimistic view, the most likely view, and the pessimistic
view of the range of the cost and schedule for the probability
and impact to the cost and schedule values. However, if no
central tendency exists for a distribution, a two-point estimate
should be used.
For schedule impact evaluation, the logic-linked project schedule
will be utilized as input to allow the random sampling process to
be tied to the critical path analysis. The project schedule
should contain sufficient logic linkage between the activities to
clearly identify critical path and near-critical path activities.
The Monte Carlo simulation process uses a random sampling process
to develop a modified duration for each risk-related task or
activity and determines the project length based on the
re-analyzed critical path, repeating the simulation to
convergence. A similar process can be executed for cost using the
project cost estimate or a detailed cost loaded schedule. Both
threats and opportunities should be analyzed.
While the use of the Monte Carlo simulation is one of the
standards of the DOE/NNSA, it does not mean that other forms of
quantitative analysis are discouraged. Other forms of
quantitative analysis may be used in conjunction with Monte Carlo
simulation. Suggested other forms of quantitative analysis that
may be considered are: decision trees, influence diagrams, system
dynamics models, and neural networks. The project should be able
to clearly explain why the particular technique was chosen and
explain why it is preferred and appropriate.
4.3.6.2.2 Additional Points of Analysis That Should be
Included
The purpose of providing the additional analysis with the Monte
Carlo simulation data is two-fold. First, Monte Carlo simulation
graphs require supporting analysis to provide the necessary
information to enable an increased understanding of a project’s
risk exposure. Second, it provides decision-makers with a basis
to engage the project team in discussions relevant to project
risks.
4.3.6.2.2.1 Planning Assumption Validation Analysis
Analyses accompanying Monte Carlo simulation data, including
graphs, should include the validation of assumptions that
serve as the basis for planning the budget and schedule of
the project from which risks arose. Since assumptions have a
basis in fact, but are not facts themselves, they should be
validated to make sure they are still operable before the
project invests in the cost of a Monte Carlo simulation
process and to ensure that parameters that will be entered
into that process are as accurate as possible.
4.3.6.2.2.2 Cost and Schedule Quantification Range
Assumption Data Gathering Process and Validation
Analysis
As the costs and schedule ranges are captured for each risk
for input into the Monte Carlo simulation runs, the
assumptions that formed the basis for those ranges should be
captured. The risks that are input may include low risks as
determined by the FPD or CPM. The reasons for capturing
those assumptions are to form an historic database for
future projects, an historic database for the current
project, a reference to substantiate how the projected
federal contingency or the contractor management
reserve/contingency was derived, and as a basis to determine
the possible range of error that may exist in the data upon
which the Monte Carlo data is based.
As with the discussion of the planning assumptions, the cost
and schedule should be validated. The validation process
consists of validating the assumptions that formed the basis
for planning the budget and the schedule as well as inputs
that went into the formation of both. The discussion of the
process used and the results should be included in the
analysis of the Monte Carlo data. Any changes to the
baseline assumptions should be highlighted in the text.
4.3.6.2.2.3 Alternative Run Analyses
The FPD or the CPM may choose to execute further Monte Carlo
simulations beyond the overall schedule and cost runs. These
may include targeted runs pertaining to specific risks or
key risks and their affects on various planned activities or
the overall project. Further groupings of risks may be
chosen and the affects simulated against the schedule and
cost of the project.
In choosing to make these runs, it is important to identify
the correlation factors (interdependencies and relationships
between risks), especially when those have become more
apparent when the runs are done after the project has been
in the execution phase for several months or years. The
constraints of how various risks or similar risks will
impact a project will demonstrate characteristics that can
be identified and captured as assumptions. While risks are
independently identified in most cases, they operate within
the confines of the project and have interdependencies,
relationships, both positive and negative, as well as
dependencies to other projects within the same program area.
In other words, there are defined relationships that should
be explored. These relationships can give rise to other
latent risks or risks that have remained undiscovered to
date until these systematic relationships are reviewed.
4.3.6.3 Project Learning Analysis
A section of the Monte Carlo simulation written analysis should
focus on the incorporation of project learning, or, in other
words, lessons learned. If the project is new, this section may
be the transference of learning from other projects. If the
analysis is an update of the Monte Carlo simulation analysis, it
should include learning from prior periods. This analysis should
include insight into how risks have thus far presented
themselves, how accurate the assumptions and estimations have
been, how those assumptions may or may not impact the simulation
results, and any other observations that the team finds are
relevant to the projections.
In the quantitative analysis, one should discuss whether bias and
perception errors could have influenced the data. Such errors in
regard to the incorporation of information from lessons learned
can arise from both an overly optimistic or pessimistic view of
project status. This view can result in a misunderstanding of the
applicability of the lesson to the project in question, caused by
the bias of the project team to the lesson presented or by a
variety of sensitivities to the data. The need to have a review
of the data and a questioning of whether any bias or
misperception could have occurred should occur in the written
analysis that accompanies the data. This analysis is often best
provided by independent subject matter experts.
In regard to the impact on the simulation results, the analysis
should focus on the calculation of the contingency values. The
usefulness of this analysis is in the follow-on risk discussions
that occur during the monthly reviews of risks wherein the
impacts of risks are reviewed along with the various assumptions
as lessons learned are applied. By bringing the learning together
with the analysis, the FPD and CPM are potentially better
prepared for how risks will react on the project or how handling
strategies will potentially mitigate the identified risks.
This process of applying lessons learned is also recommended for
projects, which perform only qualitative analysis.
4.3.6.4 Error and Variance Analysis
Depending upon the size of the project and data bank being
entered for any given simulation, it may be necessary to
subjectively estimate extreme values to bound the magnitude of
possible outcomes. If this case situation arises, it could
introduce random errors into the simulation, which could
potentially impact the results. If this occurs, it should be
disclosed and any error or bias should be discussed, as well as
any methodology—triangle distribution, for example—used to reduce
such an impact.
Risk attitude, the position that can be stated or unstated that
the organization holds towards risk, is one factor that can
influence how risk is handled and how values are assigned, and
should be included in the analysis. For example, it influences
how one views the ranges of the values and whether future values
are considered and how, when considered, they are bounded. This
line of reasoning should be discussed in the analysis.
Given that most values are best-case estimates, some error is
expected, and the introduction of some range of error should be
discussed. Even though the values generated by the Monte Carlo
simulation may be carried to several decimal points, it is
important to remember that these numerical values are indicators
not absolute values.
One suitable methodology for analysis purposes is variance
analysis. Generally, variance analysis is a tool that is used
once the project has been under way for a period of time and has
some data from which the project manager and subject matter
experts can use for determining the expected values that are used
to calculate the variance analysis.
Quantitative and qualitative analyses serve as the foundation for
continuing dialog about future risk realizations and the need for
the application of the contingency and management reserve. The
written analysis that is derived from the quantitative and
qualitative analyses should address how policy has impacted the
outcome of the data; the evaluation of the reliability, software
relevant issues, other variances which may have been introduced,
how a pattern has been applied, what it is and what choices were
made to remain consistent in the application thereof and the
impact. The benefits of this approach, relative to other
potential approaches, should be addressed.
4.3.6.5 Contingency Adequacy Evaluation
Numerous tools exist to analyze the adequacy of the contingency
valuation that has resulted from the qualitative and/or
quantitative analysis of the risks. Various tables that have been
compiled by industry are available in texts and journals and are
updated on a regular basis. These tables provide percent ranges
of the base that a contingency should represent to be considered
adequate. Further, the contingency value should be commensurate
with the maturity and type of the project, project size, and
risks, including technical and technology uncertainties.
If a quantitative risk analysis will not be conducted, estimates
for cost contingency and schedule contingency should be provided.
As a general rule, the IPT will use various inputs to determine
those values. Those inputs may be, but are not limited to:
• Historical records.
- Actual costs.
- Time impact.
• Subject matter experts.
- Delphi techniques.
- Interviewing staff, crafts, retirees, and others familiar
with similar work efforts at the site or other sites.
• Technical records such as safety analysis documents
including the risk and opportunity assessment, quality
assessments, and environmental assessments.
As the information is gathered and finalized, the data should be
analyzed for bias and perception errors. While the data will not
be systematically used for a quantitative analysis, it should
still be analyzed and perceptions scrutinized.
Note: The project’s initial estimated total cost and schedule
contingency should exceed the amount estimated to account for the
known risks because not all risks can be identified at the onset.
4.4 Risk Handling
Risk handling includes the application of specific,
pre-determined approaches to identified risks. The approach
includes identifying the risk’s owner or responsible party. While
the risk handling strategic approaches are generally applied to
high and moderate risks, they may be applied to low risks at the
discretion of the FPD or CPM.
The risk handling strategies should be compatible with the
appropriate DOE or NNSA office’s risk management policy and the
appropriate risk management plan.
Risk handling is iterative, following risk analysis, because it
involves identifying the cost and schedule associated with
implementing the risk handling strategy. Since many parameters of
the project change over time that impact the risk handling
strategies (e.g., scope of the project, available resources,
internal and external environments, technical advancements, et
al.), the process is iterative to account for these and other
impacts upon this portion of the process. One or more of these
items can change a step in a risk handling strategy or the
complete strategy which can change the cost and/or the schedule
or implementation of the risk handling strategy. The foundation
base assumptions of the risk may in fact have changed over time
and will need to be revisited as well during this iterative step.
Risk handling covers a number of risk strategies, including risk
acceptance, avoidance, mitigation, and transfer. When weighing
these approaches, the IPT should take into account the following:
• The options’ feasibility in terms of the project’s
objectives, and baseline funding and schedule.
• The expected effectiveness of the risk handling strategy
based upon the tools used by the IPT.
• The results of a cost/benefit analysis.
• The impact on other technical portions of the project.
• Any other analysis the FPD or CPM deem relevant to the
decision process.
Risk handling strategies should consider the probability and
consequence of the risk and, if deemed necessary by the risk
owner, should allow for a back-up risk handling strategy that is
documented in the risk register. If back-up risk handling
strategies are documented in the risk register, they should be
documented at the same level of detail as the primary risk
handling strategy. Documentation at the same level as the primary
strategy will ease implementation if the primary risk handling
strategy is deemed unsuitable or inadequate. Further, the cost
and necessary schedule for the back-up risk handling strategy
should be calculated and noted in the risk register.
The cost for the risk handling strategy for the primary risk
should be included in the baseline or held as contingency. There
may be occasions when a primary risk is not added to the baseline
until a change control action, such as when it is predicted
during a monthly project review or a review of lessons learned.
Risk handling strategies should be continually reviewed for their
affordability, achievability, effectiveness, and resource
availability as required by the risk management plan.
If questions arise about a risk or its handling strategy’s
potential impacts on the technical goals and objectives of the
project, a more comprehensive analysis should be conducted.
An example of a risk handling strategy:
• Establish weekly requirements and interface meetings for
design teams (set date).
• Establish a separate design review for the interfaces for
where technology interfaces occur (set date).
• Establish a separate design review for any rework that must
occur for technology interfaces (set date).
• Establish separate contractor and DOE walk-down of facility
once technologies are on-site to determine visual interfaces
concur with designs (set date).
• Establish walk-down of facility with technical staff to
ensure quality, design, safety, and other necessary staff
concur with all interface design features as physically
installed (set date).
• As with all handling strategies a trigger metric should be
established that measures when the handling strategy should
be considered for initiation by the risk owner and the
appropriate project owner whether it is the FPD or the CPM.
• Trigger Metric—RFP for two separate design contracts that
must be connected in the facility (set date).
4.4.1 Acceptance
Acceptance as a risk handling strategy should be a deliberate
decision by the FPD or CPM and documented to the risk register
and accepted by the IPT and signatories to the risk management
plan. Acceptance of the risk does not mean that the risk is
ignored. The risk should be included in the cost and schedule
contingency impact analysis.
An example of a risk that might be accepted is the fact that
there will be fewer bidders on a design-build
request-for-proposal than might be desired, but that there will
still be some competition.
Before a risk can qualify for acceptance an analysis should be
conducted to show inter-relationships. The specific method of
analysis can include the following:
• Pictorial modeling.
• Fish-bone diagramming.
• String diagramming.
• “What if” analysis systems modeling.
• Time-specific sequencing simulation modeling.
4.4.2 Avoidance/Exploit
Avoidance, as a risk handling strategy, is done by planning the
project activities in such a way as to eliminate the potential
threat. Avoidance should be considered the most desirable risk
handling strategy. However, avoidance should be analyzed for its
cost/benefit to the project within the current funded boundaries
of the project. The cost/benefit analysis should also take into
consideration the impact on the overall project and the impact on
the available funding for handling the other identified risks.
The FPD or CPM should document the decision processes used to
determine whether or not to pursue the avoidance risk handling
strategy for risks on the project. This will be evaluated by the
IPT and the signatories to the risk management plan.
Avoidance strategies often involve a change in requirements,
specifications, or practices to eliminate the risk. Avoidance can
also be the rejection of an approach to doing a piece of scope,
as the risk involved in the approach cannot be reduced to an
acceptable level. In general, to exercise this approach, another
approach that meets the cost/benefit approach should be
available. An example would be to use a known material for
construction, rather than an untested material that shows promise
under the conditions that would be present, if the costs of the
materials are within the range that is acceptable to the project
and if the unknowns presented by the untested material present
cost risks that outweigh the benefits.
The term exploit is used for positive benefit risks. To exploit
an opportunity is to attempt to ensure that it occurs. As in the
avoidance of the negative consequence risk, the thrust of the
handling strategy is to ensure that uncertainty is removed and
the opportunity definitely happens. For example, to remove the
uncertainty of whether or not human resources will be available
for an action at a certain time, one may extend the contract and
have the resources available and working on other efforts at the
site. Thus, it is ensured that the resources will be available
for the project.
4.4.3 Mitigation/Enhance
Mitigation is a risk handling strategy that is taken to reduce
the likelihood of occurrence and/or impact of an identified
negative risk or threat, or to increase the likelihood of
occurrence and/or benefit of an identified positive risk or
opportunity. The goal of a mitigation risk handling strategy is
to reduce the risk to an acceptable level.
In regard to the introduction of technologies or technologies
needing further development, the technology development plan
should be linked directly with the risk handling strategy for
risks associated with technology development or availability.
Deployment or implementation of a technology may introduce risk
that requires specific risk handling strategies.
The risk’s mitigation strategy should be developed as a step-wise
plan that can be included in the project baseline. The mitigation
plan should be analyzed to ensure that it is feasible and that
resources are available.
The term enhance is used for positive benefit risks. To enhance
an opportunity is to increase the likelihood that it will occur.
The necessity of identifying the trigger event is highlighted by
attempting to enhance the opportunity by reinforcing the
conditions identified in the trigger event.
4.4.4 Transfer/Share
The risk handling strategy of transferring risk operates
differently within the DOE or NNSA than within private industry.
In private industry, transferring risk often involves the
purchase of insurance or bonds as the transference of the risk.
The risk is passed to the insurance company that accepted the
risk for a fee. Within the DOE or NNSA, the actual risk is
transferred between the FPD and the CPM via the contract or from
one project to another, or to a program office. Risk transference
indicates a transfer of ownership, and therefore written
acceptance of the risk should be obtained before transfer is
complete. The oversight from the IPT and the risk owner should be
assigned to monitor the status of the transferred risk.
When risk has been transferred, the transfer of the risk should
be reviewed to ensure it did not create other risks. Therefore,
as was done for the acceptance strategy, an analysis review
should be conducted to fully understand inter-relationships. The
transferred risk should also be monitored by the IPT to ensure
that it does not impact the project mission and objectives.
The term “share” is associated with risks that present positive
consequences. To share a risk is to allocate the ownership of the
risk with one or more other parties. For instance, a risk could
be shared between the FPD and the contractor, between and among
various projects, or a combination thereof. In general, the risk
benefits should extend to the parties that shared the risk.
4.5 Residual Risk
Residual risk is the risk that is determined to remain after the
risk handling strategy (accept, avoid, mitigate, or transfer) has
been performed. A residual risk may end up being the same risk as
the original risk if the risk handling strategy does not reduce
or mitigate the risk or the risk is one that recurs. A residual
risk may be some portion of the original risk that remains after
the risk handling strategy is implemented. The fact that residual
risk remains does not mean that the risk handling was not
effective only that it did not completely avoid a risk remaining.
It is up to the FPD or the CPM, depending upon who owns the risk,
as to whether the residual risk will be moved to a primary risk
position. This remaining or residual risk should be qualitatively
analyzed. Through this process a decision should be made as to
when the risk planning process should stop. Those residual risks
for which no risk strategies are planned are accepted and should
be clearly communicated to the team and management.
Once it has been determined that the residual risk will remain
after the implementation of the primary risk’s risk handling
strategy, the primary risk should be closed. The residual risk
should be moved to a primary position on the risk register. Once
moved to the primary risk position, the risk handling strategy
for the risk should be reviewed and updated, if necessary. If a
back-up strategy was also logged into the risk register at the
time the residual risk was captured, it should be reviewed for
applicability also and determined if it is the better risk
handling strategy or if the two risk strategies should be merged,
blended, or completely redrafted. Following this review, the
residual risk is handled as a primary risk on the risk register
with an appropriate owner assigned. All steps that were conducted
with primary risks in regard to the baseline will need to be
accomplished with the new primary risk, if necessary, in regard
to the baseline. In other words, a review of the baseline should
be done for change in cost and schedule contingency to be made at
the discretion of the FPD and/or CPM in consultation with the
IPT.
4.6 Secondary Risk
Secondary risk is the risk that arises as a direct result of
implementing a risk handling strategy. This risk is in contrast
to a residual risk in that it is not remaining after the
implementation of a risk handling strategy. A secondary risk may
exist at the same time one is implementing a risk handling
strategy as it arises directly from the implementation of that
strategy. A secondary risk may often be able to be predicted. If
it can be predicted, the secondary risk should also appear on the
risk register. It should be assessed, although it may not be
considered a primary risk until the trigger metric has been
realized or the FPD or the CPM determines that it should be moved
to the primary risk position. Again, if the secondary risk
becomes a primary risk the FPD and/or CPM should do the analysis
of the baseline.
An example of a secondary risk: Federal risk of having to
negotiate a staged well for Area 300 B. Secondary risk: During
negotiations, the State determines that not only do they want a
staged well for Area 300 B, but they want four more staged wells
in the surrounding Area of 300 C-D. The risk of negotiating the
need for a staged well opens up the communication on wells and
may cause a secondary risk that the team feels is possible that
more wells may be requested and they estimate that number to be
four.
4.7 Risk Monitoring
Risk monitoring involves the systematic, continuous tracking and
evaluating of the effectiveness and appropriateness of the risk
handling strategy, techniques, and actions established within the
risk management plan. Monitoring is performed for individual
risks per the risk metrics and overall project risk status. The
risk monitoring process should provide both qualitative and
quantitative information to decision-makers regarding the
progress of the risks and risk handling actions being tracked and
evaluated.
Risk monitoring may also provide information that can assist in
identifying new risks or changes in the assumptions for risks
captured previously on the risk register. These results should be
used to initiate another risk identification process.
4.7.1 Risk Monitoring Process Considerations
The Risk Monitoring process should be tailored to the program
and/or project, and be described in the risk management plan. The
risk monitoring process should be more than a risk tracking
documentation process and should include the following items:
• Ensure that the risk owner is current and performing his or
her role and responsibilities.
• Ensure that risk identification is current with the
parameters of the project and initiates the rest of the risk
management continuous and iterative process within the
project culture and organization.
• Ensure that risks, including accepted and low risks, have
not changed since first identified.
• Ensure that avoidance strategies are implemented according
to schedule, and that metric indicators are showing that the
risk is not presenting itself.
• Ensure that risk handling strategies are being implemented
and executed to meet or exceed metrics for success.
• Review any back-up plans for applicability and determine if
any others need to be put into place based upon performance
of the current handling strategies.
• Review the cost and schedule contingency calculations for
the current handling strategies that are being implemented
and those that will be implemented in the near future based
upon recent performance for projected accuracy.
• Review any necessary risk management communication that may
be necessary for any current or near-term risks for
executive management, customers, stakeholders, or others and
review such communication against the risk management
communication plan.
• Ensure the recognition of the benefits and necessity of
early consideration and integration of safety and
security-related project risk into the project risk
management process.
• Ensure that the risk register and other risk-related forms
are up-to-date.
• Conduct integrated metrics management and reporting (see
Attachment 6, Cost/Benefit Analysis).
4.7.2 Risk Monitoring Methods
The following are not the only methods available and do not
exclude the use of other methods acceptable to the Program
Office.
4.7.2.1 Risk Owner Monitoring
The risk owner has a significant role in risk monitoring. As part
of the risk monitoring process, the risk owner should update
information in the risk register through an agreed upon process
with the IPT and as stated in the risk management plan. The
information that should be updated by the risk owner may require
that the risk owner inform the IPT or risk management plan
signatories.
Any changes that a risk owner makes to the risk register should
be brought to the attention of the IPT charged with monitoring
project metrics to ensure that changes in the conditions of one
risk do not impact another risk or create another potential risk.
It may be necessary to conduct an analysis study depending upon
the extent of the impact of the change to the risk register. The
FPD or the CPM, in consultation with the IPT, should make this
determination.
4.7.2.2 Self Assessment
At various junctures during the project, a FPD or a CPM may wish
to assess the risk management processes that have been
implemented. In such a case, the respective manager may wish to
use a review document designed for the particular project or a
generic checklist (see Attachment 8, Risk Identification
Checklist, and Attachment 9, Risk Monitoring Checklist).
4.7.2.3 Integrated Risk Monitoring
Integrated risk monitoring occurs when risk management metric
monitoring is integrated with other standard project metrics such
as earned value or safety metrics. The determination as to the
root cause of any negative or positive impact upon a metric
should include a determination as to whether it involved a risk
including whether it involved the positive benefit risk known as
an opportunity. The output of the reporting process can be the
input to the risk management process for further risk
identification, analysis of consequence and impact ratings, and
the analysis of the handling strategy as planned or as being
implemented.
4.7.2.3.1 Earned Value
Earned value is used to evaluate a program or project’s cost and
schedule performance. In order to integrate risk management more
fully with the earned value management system, one might identify
a number of risk evaluation metrics into the system. By
scheduling the performance of key milestones in the risk
strategies for various risks, the FPD or CPM can measure some
aspects of the performance of those risk strategies.
If a problem is noted, a corrective action could be implemented
for the risk response by using the same metric tools of cost
performance index and schedule performance index. The detailed
evaluation that would be done by the risk owner along with the
FPD and/or CPM would serve as the basis for the corrective
action.
Finally, any lessons learned should be gathered before completion
of the analysis to be shared with the team and related projects.
4.7.2.3.2 Safety Metrics
Safety metrics are used to measure the effectiveness of the
safety program, and various administrative, personnel protection,
and engineering methodologies being used to achieve worker and
public safety. Various metrics are used in the program offices.
Among those metrics are the measures of the occurrence of certain
events including electrical safety events, industrial events,
radiological events, and near miss events, etc. For the purposes
of risk management, the performance assessment that is done in
regard to safety should involve a review of events to determine
whether or not the event involved a risk, an event that could
have been predicted and thus could have been avoided.
If such a risk is determined to have been part of the safety
event, the FPD, CPM, or both should conduct a lessons learned in
accordance with the applicable safety order. All related projects
should undergo a review for an exact risk or similar risk and the
application of the lessons learned.
If the project is subject to DOE-STD-1189-2008, the key risks
should be tracked and reported per the requirements of the
standard and in relationship to the maturity of the project and
technical studies that are ongoing.
Nothing in this section eliminates the risk assessment metrics
for safety that may exist in other safety management orders or
guides.
4.7.2.3.3 Quality Metrics
Quality metrics are used to measure quality assurance and quality
control processes. Project activities and processes should have a
set of metrics. If a metric is not met, an analysis of this
shortcoming should be done to determine the reason. If the reason
for the non-achievement of the metric is a realized risk, an
analysis of the risk should be initiated to determine whether the
risk was identified, and, if not, why it was not identified.
Additionally, a reflective analysis process may be needed to
determine if the risk was hidden or latent due to other risks or
perhaps other project factors. Lessons learned should be gathered
and applied to the project and other similar projects.
If the risk was identified, the analysis should determine if the
risk operated as predicted per the assumptions, surrounding the
risk, or if the handling strategy or response was inadequate, or
if the residual risk was greater than anticipated, or if the
accepted risk was greater than what was anticipated. Again, a
full analysis should be done and shared with the project
participants and other similar projects. If the risk only allowed
for partial achievement of the metric, then the handling strategy
should be reviewed, especially if the risk is one that could
recur or is one that is found on other projects.
Nothing in this section eliminates the risk assessment metrics
for qualitative assurance that may exist in other quality
management regulations, directives, and orders.
4.7.2.3.4 Safeguards and Security Metrics
Safeguards and security metrics are used to measure the
implementation of the safeguards and security requirements for a
given project. These compliance and performance assessment
metrics as defined in DOE G 413.3-3, Safeguards and Security for
Program and Project Management, dated 11-15-07, should be
established and integrated early in the project planning. Using
these metrics on a monthly basis to highlight either the
avoidance of an identified risk or the mitigation of a risk in
this area of project integration will form a basis for continuous
and iterative risk feedback. Further, if a risk in the area of
safeguards and security is realized that was not previously
captured on the risk register, it should be reviewed and
analyzed. This reflective analysis process may be needed to
determine if the risk was hidden or latent due to other risks or
perhaps other project factors. Lessons learned should be gathered
and applied to the project and other similar projects.
Nothing in this section eliminates the risk assessment metrics
for safeguards and security that may exist in other safeguards
and securities orders or guides.
4.8 Risk Reporting
Although reporting can be either formal or informal, this guide
will focus on formal risk reporting, but acknowledges that
informal risk reporting occurs in the field through casual
conversations and interactions. While there are thresholds for
reporting requirements stated in this guide, each project might
vary based upon tailoring and risk communication requirements
that will be stated in the risk management plan and the risk
management communication plan. The use of database technology and
its filtering techniques to manage risk register information on a
monthly basis will allow the FPD or CPM to filter the risk
register list on a monthly basis. Filtering is a technique that
makes the number of risks to be reported in any given time period
those that the FPD or CPM determines should be the focus of that
reporting period. For further information, the user should refer
to the specific software package being used.
It should be noted that specific reporting per risk should be
provided by the risk owner to the FPD or the CPM.
A risk report should be filed monthly with the FPD and the IPT
and integrated with the project’s other metric reporting. Monthly
risk reporting has four primary objectives:
• Early identification of emerging risks and/or risks that
are being realized.
• Ensuring that the status of key project risks are being
tracked.
• Ensuring that risk handling strategies are being
implemented.
Although the project life-cycle risks are always important, the
focus of the monthly status report should be near term, often a
90-day rolling horizon, and changing life cycle risks should be
addressed in more detail during the periodic quantitative updates
(often performed on a quarterly basis).
The monthly risk report should contain the following (see
Attachment 10, Risk Management Reserve Report or Contingency Use
Report and Attachment 9, Risk Monitoring Checklist, for suggested
format):
• Status of the key project risks and explanations of any
significant changes.
• Status of the remaining project cost and schedule
contingency (including management reserve) and explanations
of any significant changes.
• Identification of any new high-ranking emerging risks.
• Identification of key risks ("critical risk" in DOE O
413.3A) that are active or are expected to be active during
the next 90 days.
• Review of risk handling strategies taken or due during the
previous month and their effectiveness.
• Review of risk handling strategies due during the next 90
days, including the responsible party.
• Review of any safety or security risk for which the
avoidance strategy is viewed as presenting risks which
could present secondary risks (see Attachment 10, Risk
Management Reserve Report or Contingency Use Report, and
Attachment 9, Risk Monitoring Checklist).
Discussion of the status of the risk should include more than
whether the risk is open or closed. It could include items such
as whether the trigger metric did not transpire and the risk time
has elapsed; the risk has significantly changed and is being
entered as a new risk; the risk handling strategy is being
modified; or other information that might highlight such items as
a lessons learned or new risk item. These discussions are a
necessary element of risk communication and feedback.
Any new risks, which are identified during the risk reporting
process, should be entered into the risk register. If the project
has had scope changes or other impacts that have resulted in
changes to the project’s risk profile, the risk identification
process should be re-initiated and the risk register resubmitted
either in hard copy or electronically during the reporting period
when the changes are noted (see Attachment 2, Risk Status
Report).
All risks, including those risks, which have been judged by the
IPT to be qualitatively overall low in risk, should be reviewed.
A report should be submitted by the CPM to the FPD, and by the
FPD to the appropriate designee in the program office stating any
changes in risk classifications and in the handling strategies
for near-term risks.
Risks that are of the most concern for the quarter should also be
reported in a quarterly report or in a currently existing
quarterly project report or review with the step-wise risk
handling strategy with the date metric for risk reporting.
In addition to the information contained in the monthly risk
report, the quarterly report should contain the following:
• An updated project key risk table that reflects the current
project level risks.
• An updated risk register including handling actions for
risks ranked greater than low with their associated due
dates and responsible party for the risk handling
strategy.
• Identification, one level below the project level, of risks
which have the largest potential to impact the project if
their likelihood or their impacts were to increase over
current projections.
If changes in risk handling actions and/or risk levels are
indicative of a forecasted shortfall, an updated quantitative
analysis assessing the adequacy of project cost and schedule
contingencies is recommended.
4.9 Risk Feedback
Risk feedback is a continuous and iterative activity throughout
the risk management process. Participants in the risk management
process should provide feedback throughout the program or
project. This feedback process begins with the initial
identification of the overall risk of the project at the mission
need phase of the project, CD-0, to the project close out, CD-4,
and the capture of the final lessons learned (see Section
4.3.6.3, Project Learning Analysis). One area of particular need
for risk feedback concerns the gathering of requirements for
input into the cost and schedule bounding for the purposes scope
determination for the project and other related acquisition
actions. This process must begin as early as possible in the
project and must be a thorough risk and requirements feedback
process.
The process of providing feedback can be done either in a formal
or informal manner—either in a written or oral format. However,
it is recommended that wherever possible, feedback should be
provided in a formal, written format to ensure that it is
captured, and that it is recorded and received by the appropriate
project official, whether it is the risk owner or the FPD and/or
the CPM.
The risk management plan may prescribe the method for certain
types of risk feedback and presentation. The types of risk
feedback that the risk management plan should prescribe, but are
not limited to, include reporting, official responses to reports,
and maintenance of the risk register.
5.0 RISK DOCUMENTATION AND COMMUNICATION
5.1 Project Execution Plan
The risk management plan should be included in or referenced in
the project execution plan.
5.1.1 Baseline Management
Changes to the baseline due to risks not identified will
generally result in the filing of a change control document. When
a baseline update has occurred, a full review of the risks should
be done to ensure that the baseline change has not resulted in
other risks that may occur in the future due to the change either
in schedule, budget, or scope. Those risk handling strategies not
part of the project baseline will have cost and schedule impacts,
if implemented at a later date.
If the project has had scope changes or other impacts that have
resulted in changes to the project’s risk profile, the risk
identification process should be re-initiated and the risk
register resubmitted either in hard copy or electronically during
the reporting period when the changes are noted.
5.1.2 Phase Integration
Risk management and its processes should be tailored to the
specific project phase. For example, risk management should be
started on a project when it will have the most impact, which
means, generally, at the development of the mission need
statement. The degree to which it can be started will depend upon
each project and the knowledge possessed at the time.
It is necessary to ensure that risks are represented and risk
handling actions are suitable for the phase of the project. In
other words, the response can satisfy a cost/benefit analysis for
the phase or timing of the implementation of strategy whether it
is early in the project or late, and that the schedule to
implement can be done within the project without impacting other
milestones or critical activities.
5.1.3 Acquisition Strategy
When developing the acquisition strategy documentation, the FPD
with the Contracting Officer should direct attention to risk
identification in the following areas as input to the acquisition
decisions:
• Cost—as it relates to the facility, technology, or system
to achieve the project’s mission objective(s).
• Design and Engineering—as it relates to the facility,
technology, or system to achieve the design and/or
engineering objectives.
• Functional—as it relates to the facility, technology, or
system to perform or meet project requirements.
• Integration—as it relates to the integration of any
hardware or software for various systems for the facility,
technology, or system and the demonstration of this
integration to meet project requirements.
• Procurement Vehicles/Process—as it relates to the
procurement decision process, contract requirements,
available competition, market conditions, and other
constraints.
• Regulatory—as it relates to the physical site,
environmental conditions and process needs, facility
requirements, and any other project specific regulatory
requirements.
Other risk categories may need to be reviewed within the
acquisition strategy and planning activity and, as they are
captured, they should be tracked in the risk breakdown structure
under the appropriate category and in the risk register.
5.2 Risk Management Plan
The risk management plan is the governing document for the risk
management process on a project. The risk management plan should
be reviewed and revised on at least an annual basis. The risk
management plan includes by reference the risk register, risk
analysis, and other risk data and risk database information that
is updated more frequently, but is not reissued whenever such
data is changed or updated.
The sections of this guide that mention separate risk management
plans and risk registers are not meant to state that a combined
federal/contractor risk management plan and/or risk register
cannot be done. A combined federal/contractor risk management
plan and/or risk register may be done as part of the tailoring
process and if acceptable to the program office.
Note: The FPD or the CPM can decide to tailor the risk management
plan based upon criteria such as the size, complexity, budget,
risk level, resources, technical maturity level, and other
considerations deemed relevant. The decision to submit combined
or separate plans should be made based on program guidelines
and/or the needs and requirements of the project.
The risk management plan should include the following sections:
I. Introduction (may be contained in project execution plan)
a. Program/project summary
b. Responsibility assignment matrix (see Attachment 3,
Risk Responsibility Assignment Matrix)
c. Program/project acquisition strategy summary
d. Key definitions
e. Key requirements documents and regulatory drivers
f. Assumptions and constraints
II. Risk management process
a. Risk planning
b. Risk assessment
c. Risk identification
d. Risk analysis
e. Risk handling
f. Risk monitoring
g. Risk feedback
III. Risk documentation and communication
IV. Conclusion
5.3 Risk Management Communication Plan
Communication is identified in DOE O 413.3A as a key principle to
project success. To ensure project success the risk management
plan should address how information related to risk, and risk
status is communicated to the project team and stakeholders. This
communication information can be addressed in either the project
execution plan or a communication plan or can be included in the
risk management plan. A separate risk management communication
plan could also be developed.
The risk management communication plan should contain the
following sections:
I. Background and purpose
a. Responsible office and key individuals
b. Necessary oversight and signatory responsibilities
II. Project overview
III. Target objectives
a. Development of standard, and as needed, communication
formats and messages for identified risk stakeholders
b. Development of communication flow diagrams
IV. Strategy
a. Statement of overall strategy elements
b. Assumptions and uncertainties
c. Process for validating and verifying assumptions and
uncertainties
V. Key target stakeholders
a. Identification process
b. Known stakeholders
VI. Identified communication channels for each target
stakeholder grouping
a. Process for identifying key points of contact
(1) Primary point-of-contact
(2) Back-up point-of-contact
b. Process for identifying key points of contact for
emergency communications
VII. Key messages
a. Site communication requirements
(1) Goals and objectives
(2) Processes
b. When certain communications may be issued
c. Definition of various modes of communication
d. Situational requirements
e. Definition of special circumstances
f. Definition of special approval channels
g. Communication development
(1) Who should be involved in construction of
communications
(2) Who should review
h. Standard messages
i. Key interfaces
j. Communication distribution and feedback
VIII. Roles and responsibilities
a. Identify all parties
b. Responsibility assignment matrix
IX. Overview metrics for responsible persons
X. Message approval process
XI. Revisions and updates
6.0 TAILORING OF RISK MANAGEMENT
The standard risk management process applies to every project, as
there is a need to manage risks and opportunities to improve the
likelihood of meeting the project’s objectives. The planning,
identification, analysis, handling, monitoring and feedback steps
are applicable to all projects. The process is tailored based
upon the complexity, size and duration of the project; initial
overall risk determination; organizational risk procedures;
available personnel and their skill levels for performing risk
management; and available relevant data and its validation. The
final determination for tailoring the level of risk management to
be executed on those projects will be made by the FPD and/or the
CPM and should be documented in the project execution plan.
Tailoring of the risk management process generally includes
selection of what risks to actively manage based on risk level,
determination whether to perform a quantitative analysis, types
of analysis to be performed, and types and frequency of reporting
and monitoring.
7.0 ATTACHMENTS
The forms in this section are only suggested formats and may be
modified as required by the program office, site office, or the
project. All forms can be modified to work with numerous
commercially available software programs. Fields suggested for
forms may be supplemented or deleted as necessary, although
certain fields may be noted as necessary for the purposes of
analysis or reporting within the text of the guide regarding that
type of reporting. Before modifications are made to the fields on
the forms, verify that the field is not one that is considered
necessary for the purposes of analysis or reporting.
Attachment 1: Risk Breakdown Structure—Example One
See the graphic in the PDF
See reference – Hillson, D. A. (2007), “Understanding risk
exposure using multiple hierarchies,” published as part of 2007
PMI Global Congress EMEA Proceedings – Budapest.
Attachment 1: Risk Breakdown Structure—Example Two
See the table in the PDF
Attachment 2: Risk Status Report
Item Number Comments
1 Risks Open _________ __________________________
2 Risks Closed _________ __________________________
3 Monitoring
Trigger Pending Within
Three Months _________ __________________________
4 Residual Risk
Handling Response
Enacted _________ __________________________
5 Residual Risk
Moved to Primary _________ __________________________
6 Secondary Risk
Moved to Primary _________ __________________________
Attachment 3: Risk Responsibility Assignment Matrix
-----------------------------------------------------------------
Federal Integrated Subject Contractor Other--
Project Project Matter Project Identify
Director Team Expert Manager
-----------------------------------------------------------------
Risk Planning
Risk
Identification
Qualitative
Analysis
Quantitative
Analysis
Handling
Response
Monitoring
and Control
Risk
Communication
Legend
Responsible Accountable Reviews Approves Contributes Prepares
Attachment 4: Probability Scale/Schedule Consequence Criteria
Probability Scale Example
Very High >90%
High 75-90% Moderate/High 60-75%
Moderate 26-74% Moderate/Moderate 40-60%
Low 10-25% Moderate/Low 25-40%
Very Low <10%
Schedule Consequence Scale Example
Very High 12-24 months
High 12-18 months Moderate/High 9-12 months
Moderate 3-12 months Moderate/Moderate 6-9 months
Low 0-3 months Moderate/Low 3-6 months
Very Low 0-0.5 months
Cost Consequence Scale Example
Very High $10M-$100M
High $1-$10M Moderate/High $0.5-$1.0M
Moderate $100K-$1M Moderate/Moderate $250-$750K
Low $10-$100K Moderate/Low
$100K-$250K
Very Low <$10K
Notes:
• The criteria for each category may be adjusted depending on
the size and duration of the project. For instance, a
6-month impact may be Moderate for a 10-year project, but
Very High for a 2-year project. Similarly, a $1M impact may
be very high for some projects where other longer/larger
projects may have risks that exceed $1B.
• A category can be expanded to facilitate the elicitation of
risks from subject matter experts. In the above probability
and schedule scales, the “Moderate” scale was expanded.
• Categories may be overlapping or non-overlapping.
Attachment 5: Risk Register
The risk register or risk log is a database often captured in a
database such as Access or Excel or other risk management
software tool. The format is dictated by the size of the project
and the ease of compiling the necessary reports. Following are
the names of the fields that should appear in the risk register
and a description of those fields. The database should be capable
of generating reports based upon querying various fields and
dates for open risks and trigger dates as well as handling
responses that are currently operable.
Risk: Risk as identified and should include the cause, the risk,
and the effect. The preferred statement should be in the
affirmative to gain the most effective risk handling responses or
strategies.
Risk Identification Number: Unique identification number for the
risk.
WBS: Work Breakdown Structure identification number.
Risk Owner: Person responsible for tracking, monitoring,
documenting, and ensuring the handling response or strategy is
implemented and reported upon.
Risk Category: Category assigned for grouping or from Risk
Breakdown Structure analysis.
Risk Status: Open or closed.
Risk Assumptions: Any assumptions pertaining to the risk itself.
The identification of assumptions may be clues to other risks.
Risk Probability and Basis: Likelihood of this event occurring.
Use the appropriate qualitative risk analysis matrix.
Risk Consequence and Basis: Outcome of this event. Use the
appropriate qualitative risk analysis matrix.
Risk Level: The intersection of the probability and consequence
on the appropriate qualitative risk analysis matrix, which
determines the overall potential risk impact to the project.
Risk Monitoring Trigger: Early warning signs that this risk is
about to occur.
Success Metric: Measure by which the Federal Project Director or
Contractor Project Manager will know that the avoidance strategy
or handling response or strategy has been successful.
Avoidance Strategy: If there is an avoidance strategy to
eliminate risk completely it should go in this field.
Risk Handling Strategy: Step-by-step (similar to a project plan)
approach to eliminating or reducing the risk if no avoidance
strategy is immediately available; includes the dates for
completion.
Cost (for risk handling strategy): Necessary cost for
implementing the handling strategy.
Cost Assumptions: Assumptions that relate to the cost contingency
values.
Schedule (for handling strategy): Necessary schedule for
implementing the risk handling strategy.
Schedule Assumptions: Assumptions that relate to the schedule
contingency values.
Residual Risk: Remaining risk once the risk handling strategy is
completed.
Risk Handling Strategy for Residual Risk: May be filled in
depending upon the level of risk perceived by the Federal Project
Director or the Contractor Project Manager.
Residual Risk Probability and Basis: Likelihood of this event
occurring. Use the appropriate qualitative risk analysis matrix.
Residual Risk Consequence and Basis: Outcome of this event. Use
the appropriate qualitative risk analysis matrix.
Residual Risk Level: The intersection of the probability and
consequence on the appropriate qualitative risk analysis matrix,
which determines the overall potential risk impact to the
project.
Secondary Risk: Risk arising as a direct result of the
implementation of a risk handling strategy.
Secondary Risk Probability and Basis: Likelihood of an event
occurring. Use the appropriate qualitative risk analysis matrix.
Secondary Risk Consequence and Basis: Outcome of an event. Use
the appropriate qualitative risk analysis matrix.
Secondary Risk Level: The intersection of the probability and
consequence on the appropriate qualitative risk analysis matrix,
which determines the overall potential risk impact to the
project.
Attachment 6: Cost/Benefit Analysis
Often captured as Benefit/Cost = Return on Investment (or
Investment Outcome).
For the purposes of this Guide, the steps are:
• Identify the costs and benefits
• Quantify in units
• Calculate units into dollar value
• Calculate costs and benefits into time
• Project the net benefits and costs
These benefits and costs can be distributed over time using the
same Monte Carlo simulation methodology, if desired.
Attachment 7: Opportunity Matrix
See the table in the PDF
Attachment 8: Risk Identification Checklist
Context for use of this checklist:
This checklist is to be used as a follow-up to a brainstorming
session or other methodology such as interviews, risk breakdown
structures or diagramming techniques to ensure that all currently
identified DOE areas of concern have been covered. It is not
intended as a complete checklist and may be used in conjunction
with other checklists as the user may see fit. The checklist
should not be used in lieu of the brainstorming session and other
methods of risk identification, but as a checklist is intended to
check the work done by the risk identification team members.
1. Front-End Planning Risks
• Expectations and/or requirements that:
- Have not been identified.
- Are unrealistic.
- Are incomplete.
- Are unstable.
- In conflict with each other.
• Incomplete or inaccurate identification of constraints:
- Funding/budget resources.
- Political support.
- Staff and contractor resources.
- Procedural.
• Unrecognized or underestimated complexities caused by:
- The number of systems, structures, components.
- The number of requirements and constraints.
- Technical challenges.
- Technical interfaces.
- Organizational and functional interdependencies.
- Nonlinearity.
- Unstable or dynamic environments.
- Schedule demands.
• Excessive, unrealistic, or unrecognized assumptions.
2. Staffing Risks (Federal and Contractor)
• Inadequate staffing for the size, complexity, and/or
challenges of the project.
• Inadequate formal education/certification/training.
• Personnel/organizations lack experience on similar
projects.
• Unwillingness to seek out or utilize lessons learned by
others.
• Inadequate “soft skills,”
• Inadequate cognitive skills.
- Lack of situational awareness.
- Inabilities to recognize evolving patterns (connect
the dots) and/or recognize warning signs.
- Inability to foresee and avoid the obstacles the
project will experience.
- Inability to adjust to changing situations or
environments.
- Inability to foresee the secondary effects or
unintended consequences of decisions or actions.
3. Organizational Risks (Federal and Contractor)
• Lack of organizational alignment.
- Different organizational cultures.
- Different organizational priorities.
- Different levels of motivation.
• Unclear or overlapping roles, responsibilities, and/or
authority.
• Organizational fragmentation/excessive outsourcing and
use of subcontractors.
• Lengthy decision/approval chains.
4. Site Risks
• Access constrains.
• Underground/soil conditions.
• As-built conditions.
• Utility availability/capabilities.
• Coordination with other construction activities.
5. Risk of Omission of Key Cost and Schedule Drivers
• Document, design, and/or construction rework.
• Learning curves.
- Individual.
- Corporate.
• Coordination/integration of individual tasks/efforts.
• Iterative development.
• Approval times.
• Logistics problems.
• Supply chain management challenges.
• Lack of applicable productivity, cost, and schedule
data/benchmarks.
- For spot estimates.
- For probability distributions.
• Market related risks (see below).
6. Market Related Risks.
• Limited vendor/contractor availability and/or interest
because of external market conditions.
- Availability of other work (the existence of a
seller's market).
- Volatile prices.
- Limited or uncertain availability of materials,
labor, components, and/or construction equipment.
- Limited availability of financing to cover cash flow
delays.
• Reduced vendor/contractor interest because of contract
imposed terms and conditions that increase their risks.
- No recovery of damages for owner-caused delays.
- Full indemnity for damages.
- Ambiguous acceptance criteria.
- Financial responsibilities for force majeure.
- Cumulative impact of multiple change orders.
- Owner-mandated subcontractors.
- Differing site conditions.
- Transfer of design responsibility to constructors
and suppliers.
- Waiver of claims due to time limits.
- Standards of care clauses such as “highest and best
industry standards” and “in a workmanlike manner,”
- Fixed price contracts.
• Reduced vendor/contractor interest because of the
uniqueness of the tasks or performance requirements.
7. Ineffective or Incomplete Governmental Oversight
• Delayed problem recognition and resolution because of:
- Inadequate systems for measuring performance.
- Construction/procurement releases before final
designs are sufficiently complete.
- Ineffective project reviews, inadequate use of
project management tools.
- Lengthy/ineffective feedback loops.
8. Technical Alignment Risks (Hazard Category 1, 2, & 3
Projects)
• Design margins/degree of conservatism.
• Definition, selection, and implementation of quality
assurance requirements.
• Safety-class and significant fire protection systems.
- Fireproofing of structural steel.
- Combustible loadings.
- Degradation of HEPA filters.
- Fire detection and suppression system activation
mechanisms.
- Hydrogen & flammable gas generation/accumulation.
• Seismic/structural.
- Ground motion.
- Adequacy of geotechnical investigations.
- Soil settlement.
- Soil-structure interaction analyses.
- Load paths for seismic and settlement induced
forces.
- Finite element analysis.
- Structural computer codes.
• Confinement
- Strategy.
- Adequacy of confinement barriers.
- Magnitude of the radiological source term.
• Criticality standards.
• Chemical process safety.
• Technical defensibility of calculations and designs.
Attachment 9: Risk Monitoring Checklist
Item
Number Item Yes/No Comment
1 Risk handling strategy was implemented
as planned
2 Risk handling strategy was effective
3 Back-up risk handling strategy was required
to be implemented
4 Risk assumptions were valid
5 Project assumptions were valid
6 Risk monitoring trigger was valid
7 Risks were correctly noted in risk reports
8 Risk was on team meeting agendas
9 Risk monitoring was conducted per the Guide
10 Risk was integrated into Earned Value
discussions
11 Were unidentified risks discovered
12 Was contingency associated with a given
risk sufficient
13 Were risks captured in the risk register
and updated
14 Was a risk brainstorming session or
scenario planning session used to identify risks
15 Was a subsequent session for identification
of risk conducted to update the risks identified
16 Were lessons learned captured during
the risk process
17 Were lessons learned distributed during
the risk process to the project team
18 Were lessons learned distributed during
the risk process to other project teams
19 Were any systems analysis or decision
analysis methodologies applied, especially for such
items as technology readiness level implementation
Attachment 10: Risk Management Reserve Report or Contingency Use
Report
The CPM will generally use the management reserve report. If
funds are applied outside of risks captured on the risk register,
the explanation should be captured on the report and accepted by
the site office FPD.
Management Schedule
Risk Realized: Reserve Contingency
ID #, WBS # Expended Expended Comments
------------ ---------- ---------- -----------------
------------ ---------- ---------- -----------------
------------ ---------- ---------- -----------------
------------ ---------- ---------- -----------------
------------ ---------- ---------- -----------------
------------ ---------- ---------- -----------------
------------ ---------- ---------- -----------------
Attachment 11: Glossary
This glossary of terms is derived within the context of how terms
are used in the guide.
Acquisition Strategy: A high-level business and technical
management approach designed to achieve project objectives within
specified resource constraints. It is the framework for planning,
organizing, staffing, controlling, and leading a project. It
provides a master schedule for activities essential for project
success, and for formulating functional strategies and plans.
Activity: An element of work performed during the course of a
project. An activity normally has an expected duration, an
expected cost, and expected resource requirement.
Actual Cost: The costs actually incurred and recorded in
accomplishing work performed.
Assumptions: Factors used for planning purposes that are
considered true, real or certain. Assumptions affect all aspects
of the planning process and of the progression of the project
activities. (Generally, the assumptions will contain an element
of risk.)
Baseline: A quantitative definition of cost, schedule, and
technical performance that serves as a base or standard for
measurement and control during the performance of an effort; the
established plan against which the status of resources and the
effort of the overall program, field program(s), project(s),
task(s), or subtask(s) are measured, assessed, and controlled.
Bias: A repeated or systematic distortion of a statistic or
value, imbalanced about its mean.
Brainstorming: Interactive technique designed for developing new
ideas with a group of people.
Change Control: A process that ensures changes to the approved
baseline are properly identified, reviewed, approved, implemented
and tested, and documented.
Communication Planning or Plan: Process and plan for determining
the information and communication needs of the project/program
stakeholders. Identifies who needs what information, when they
will need the information, and how it should be presented,
tracked, and documented.
Consequence: Outcome of an event. (Normally includes scope,
schedule, and cost.)
Correlation: Relationship between variables such that changes in
one (or more) variable(s) is generally associated with changes in
another. Correlation is caused by one or more dependency
relationships. Measure of a statistical or dependence
relationship existing between two items estimated for accurate
quantitative risk analysis.
Decision Analysis: Process for assisting decision makers in
capturing judgments about risks as probability distributions,
having single value measure, and putting these together with
expected value calculations.
Delphi Technique: Technique used to gather information used to
reach consensus within a group of subject matter experts on a
particular item. Generally a questionnaire is used on an agreed
set of items regarding the matter to be decided. Responses are
summarized, further comments elicited. The process is often
repeated several times. Technique is used to reduce bias in the
data and to reduce the bias of one person, one voice.
Estimate: Assessment of the most likely quantitative result.
(Generally, it is applied to costs and durations with a
confidence percentage indication of likelihood of its accuracy.)
Expert Interviews: Process of seeking opinions or assistance on
the project from subject matter experts (SMEs).
External Risks: Risks outside the project control or global risks
inherent in any project such as global economic downturns, trade
difficulties affecting deliverables such as construction
materials or political actions that are beyond the direct control
of the project.
Feedback: System concept where a portion of the output is fed
back to the input.
Fishbone Diagram: Technique often referred to as cause and effect
diagramming. Technique often used during brainstorming and other
similar sessions to help identify root causes of an issue or
risk. Structure used to diagram resembles that of a fish bone.
Impact Scores: Convergence of the probability and consequence
scores.
Initiation: Authorization of the project or phase of the project.
Internal Risks: Risks that the project has direct control over,
such as organizational behavior and dynamics, organizational
structure, resources, performance, financing, and management
support.
Key Risk: Key risks are a set of risks considered to be of
particular interest to the project team. These key risks are
those estimated to have the most impact on cost and schedule and
could include project, technical, internal, external, and other
sub-categories of risk. For example on a nuclear design project,
the risks identified using the “Risk and Opportunity Assessment”
process may be considered a set of key risks on the project.
Lessons Learned: Formal or informal set of “learnings” collected
from project or program experience that can be applied to future
projects or programs after a risk evaluation. Can be gathered at
any point during the life of the project or program.
Mitigate: To eliminate or lessen the likelihood and/or
consequence of a risk.
Opportunity: Risk with positive benefits.
Primary Risk: Initial risk entry in the risk register. A residual
or secondary risk can become a primary risk if in the case of a
residual risk the primary risk is closed and the Federal Project
Director and/or Contractor Project Manager determines the
residual risk should be made the primary risk or the risk entry
in the risk register. The secondary risk can become the primary
risk in the risk register if the Federal Project Director and/or
Contractor Project Manager determine that it should become the
risk entry based upon the realization of the trigger metric or
other determining factor.
Probability: Likelihood of an event occurring, expressed as a
qualitative and/or quantitative metric.
Program: A portfolio of projects and/or other related work
efforts managed in a coordinated way to achieve a specific
business objective.
Project Risk: Risks that are captured within the scope, cost, or
schedule of the project.
Qualitative Risk Analysis: Involves assessing the probability and
impact of project risks using a variety of subjective and
judgmental techniques to rank or prioritize the risks.
Quantitative Risk Analysis: Involves assessing the probability
and impact of project risks and using more numerically based
techniques, such as simulation and decision tree analysis for
determining risk implications.
Residual Risk: Risk that remains after risk strategies have been
implemented.
Risk: Factor, element, constraint, or course of action that
introduces an uncertainty of outcome, either positively or
negatively that could impact project objectives. This definition
for risk is strictly limited for risk as it pertains to project
management applications in the development of the overall risk
management plan and its related documentation and reports.
Risk Acceptance: An informed and deliberate decision to accept
consequences and the likelihood of a particular risk.
Risk Analysis: Process by which risks are examined in further
detail to determine the extent of the risks, how they relate to
each other, and which ones are the highest risks.
Risk Assessment: Identification and analysis of project and
program risks to ensure an understanding of each risk in terms of
probability and consequences.
Risk Assumption: Any assumptions pertaining to the risk itself.
Risk Breakdown Structure: Methodology that allows risks to be
categorized according to their source, revealing common causes of
risk on a project.
Risk Category: A method of categorizing the various risks on the
project to allow grouping for various analysis techniques such as
Risk Breakdown Structure or Network Diagram.
Risk Communication: An exchange or sharing of information about
risk between the decision-maker(s), stakeholders, and project
team. (The information can relate to various information sources
such as the existence, nature, form, probability, severity,
acceptability, treatment, or other aspects of risk.)
Risk Documentation: The recording, maintaining, and reporting
assessments, handling analysis and plans, and monitoring results.
Risk Handling Strategy: Process that identifies, evaluates,
selects, and implements options in order to set risk at
acceptable levels given project constraints and objectives.
Includes specific actions, when they should be accomplished, who
is the owner, and what is the cost and schedule.
Risk Identification: Process to find, list and characterize
elements of risk.
Risk Management: The handling of risks through specific methods
and techniques.
Risk Management Plan: Documents how the risk processes will be
carried out during the project/program.
Risk Mitigation: Process to reduce the consequence and/or
probability of a risk.
Risk Monitoring and Tracking: Process of systematically watching
over time the evolution of the project risks and evaluating the
effectiveness of risk strategies against established metrics.
Risk Owner: The individual responsible for managing a specified
risk and ensuring effective treatment plans are developed and
implemented.
Risk Planning: Process of developing and documenting an
organized, comprehensive, and interactive strategy and methods
for identifying and tracking risk, performing continuous risk
assessments to determine how risks have changed, developing risk
handling plans, monitoring the performance of risk handling
actions, and assigning adequate resources.
Risk Register: Database for risks associated with the project.
(Also known as risk database or risk log.)
Risk Threshold: Defined or agreed level of acceptable risk that
risk handling strategies are expected to meet.
Risk Transfer: Movement of the risk ownership to another
organizational element. (However, to be successfully and fully
transferred, the risk should be accepted by the organization to
which the risk is being transferred.)
Secondary Risk: Risk arising as a direct result of implementing a
risk handling strategy.
Simulation, (Monte Carlo): Process for modeling the behavior of a
stochastic (probabilistic) system. (A sampling technique is used
to obtain trial values for key uncertain model input variables.
By repeating the process for many trials, a frequency
distribution is built up, which approximates the true probability
distribution for the system’s output. This random sampling
process, averaged over many trials, is effectively the same as
integrating what is usually a very difficult or impossible
equation.)
String Diagram: Technique used to analyze the physical or
proximity connections within a process. Technique is often used
to find latent risks.
Technical Risk: Risks that include disciplines such as
mechanical, electrical, chemical engineering, safety, safeguards
and security, chemistry, biology, etc.
Threat: Risk with negative consequences.
Trigger Metric: Event, occurrence or sequence of events that
indicates the risk may be about to occur, or the pre-step for the
risk indicating that the risk will be initiated.
Appendix A: References
DoD Acquisition, DoD Acquisition Risk Management Guide, Sixth
Edition, Version 1, August 2006.
DOE CIO Guidance Cs-3, Risk Management Guidance, October 10,
2007.
DOE, Office of Environmental Management, Risk Management Policy,
February 23, 2007.
OMB M-07-24, Memorandum for the Heads of Executive Departments
and Agencies, “Updated Principles for Risk Analysis,” September
19, 2007.
NASA Procedural Requirements 8000.4, Risk Management, February 1,
2007.
National Research Council of the National Academies, The Owner’s
Role in Project Risk Management, 2005.
DOE O 413.3A, Program and Project Management for the Acquisition
of Capital Assets, dated 7-28-06.
DOE G 413.3-Series Guides.
DOE-STD-1189-2008, DOE Standard, Integration of Safety Into the
Design Process, March 2008.
Checklist References
http://www.risk-management-basics.com/risk-management-checklists.
shtml, Risk Management Basics, March 2006.
http://www.wiredforgrowth.com/risk-tools/risk-checklists/?cprofil
e=N, Wired for Growth, 2008.
http://it.toolbox.com/blogs/enterprise-solutions/risk-management-
checklist-22039, Information Technology Toolbox, 2008.
http://international.fhwa.dot.gov/riskassess/risk_hcm06_b.cfm,
U.S. Dept. of Transportation, Federal Highway Administration,
November 2007.
http://www.calstate.edu/cpdc/cm/forms/, California State
University, June 2008.
http://www.startwright.com/project1.htm, StartWright, January
2006.
General References
Baker, “Analyzing Risks,” PM Network, March 2003.
Barkley, Project Risk Management: A Proactive Approach.
Management Concepts, Vienna, VA. 2002.
Conrow, Effective Risk Management: Some Keys to Success, 2d.
American institute of Aeronautics and Astronautics, Inc., Reston,
VA. 2003.
Cooper, “Toward a Unifying Theory for Compounding and Cumulative
Impacts of Project Risks and Changes,” Innovations: Project
Management Research 2004, Slevin, Cleland, and Pinto, eds. PMI,
Newtown Square, PA. 2004.
Cooper, Grey, Raymond, & Walker, Project Risk Management
Guidelines: Managing Risk in Large Projects and Complex
Procurements. John Wiley & Sons, Ltd., West Sussex, England.
2005.
Fundamentals of Risk Analysis and Risk Management, Molak, ed.
Lewis Publishers, Boca Raton, Fl. 1997.
Hillson, D. A. (2007), “Understanding risk exposure using
multiple hierarchies,” published as part of 2007 PMI Global
Congress EMEA Proceedings – Budapest, www.pmi.org.
Hillson and Murray-Webster, Understanding and Managing Risk
Attitude. Gower, Burlington, VT. 2005.
Hoffman, W., “Balancing Act,” PM Network, Newtown Square, PA. May
2006.
Hoffman, E. “NASA Reduces Uncertainty and Minimizes Risks with
Project Methods,” PM Network, Newtown Square, PA. June 2003.
Hutchins, “Ready for Risk Reporting?” PM Network, Newtown Square,
PA. November 2002.
Ingebretsen, “Afraid of a Little Risk?” PM Network, February
2005.
Jedd, “Risking Less,” PM Network, Newtown Square, PA. September
2005.
Kendrick, Identifying and Managing Project Risk: Essential Tools
for Failure Proofing Your Projects. AMA, New York, NY. 2003.
Levine, Project Portfolio Management: A Practical Guide to
Selecting Projects, Managing Portfolios, and Maximizing Benefits.
Jossey-Bass, San Francisco, CA. 2005.
Logue, “20/20 Foresight,” PM Network, Newtown Square, PA.
September 2004.
Maytorena, Winch, Kiely, Clarke, and Dalton, “Identifying Project
Risks: A Cognitive Approach,” Innovations: Project Management
Research 2004. PMI, Newtown Square, PA. 2004.
Mulcahy, Risk Management: Tricks of the Trade® for Project
Managers—A Course in a Book®. RMC Publications, 2003.
Pfeffer and Sutton, The Knowing-Doing Gap: How Smart Companies
Turn Knowledge into Action. Harvard Business School Press,
Boston, MA. 2000.
Project Management Body of Knowledge 2004 Guide. Newtown Square,
PA. 2004.